Cheat sheet
Rebar takeoff and bar bending schedule (UAE, BS 8666)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Outside dimensions overstate the bar. Take the bend deductions back, and count each zone of links once.
- How it is built
- Cut length of a link = 2 × (A + B + C) − 2.5 × bend radius − 5 × bar diameter
- Cut length of a top bar = A + B + C − bend radius − 2 × bar diameter
- Total length of a mark = Number of bars × Cut length of one bar
- Usual mistake
- Outside dimensions count each corner twice. Take 2.5r + 5d back for the bends.
- At work
- Every bar bending schedule sent to the steel yard is built this way, one bar mark at a time.
- Rule
- Count spaces, then add one. Lap once per joint. Cover comes off both ends of every bar.
- How it is built
- Bars across the slab = (Distance between first and last bar ÷ spacing, rounded up) + 1
- Length of a mark 05 line = Slab length less cover + one lap
- Mesh sheets = Sheets along the length × Sheets across the width
- Usual mistake
- One line is two bars lapped once, in the middle. The ends do not lap.
- At work
- Site engineers check the bar count of every slab before the concrete pour, against this same schedule.
- Rule
- The bill measures net steel; the order buys the waste too. Round each element, then multiply.
- How it is built
- Weight of one bar mark = Total length × Mass per metre, diameter² ÷ 162
- Net tonnes of a size = Weight per element × Number of elements ÷ 1000
- Order quantity = Net tonnes of each size × (1 + its waste) + the other sizes
- Usual mistake
- The bill measures net weight. Waste goes into the order and into the rate.
- At work
- Quantity surveyors bill net steel, and the site orders the same steel plus waste from the supplier.
- Rule
- Waste loads the supply price only. Labour is paid on the net tonne; the markup is one row.
- How it is built
- Rate of a size = Supply × (1 + waste) + Cut and bend + Fix
- Package price = Rates × net tonnes + Overhead and profit
- Average rate per net tonne = Grand total of the bill ÷ Sum of the net tonnes
- Usual mistake
- Waste loads the supply price only. Cutting and fixing are paid on the net tonne.
- At work
- Rebar subcontractors price every package like this: supply with waste, then cutting, bending and fixing.
- Rule
- A change of size comes out and goes in. New diameter, new cut length, then the bill rates and one markup.
- How it is built
- Net change of a size = Weight added − Weight omitted
- Value of the change = Net tonnes × bill rate, each size + Overhead and profit
- Usual mistake
- The old bars come out of the structure. Omit them at the bill rates and add the new ones.
- At work
- Revised drawings arrive on every job; the QS re-measures the change and values it at bill rates.