Cheat sheet

Rebar takeoff and bar bending schedule (UAE, BS 8666)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Beam B7: bars by shape code

Theory (9 min)
Rule
Outside dimensions overstate the bar. Take the bend deductions back, and count each zone of links once.
How it is built
  • Cut length of a link = 2 × (A + B + C) − 2.5 × bend radius − 5 × bar diameter
  • Cut length of a top bar = A + B + C − bend radius − 2 × bar diameter
  • Total length of a mark = Number of bars × Cut length of one bar
Usual mistake
Outside dimensions count each corner twice. Take 2.5r + 5d back for the bends.
At work
Every bar bending schedule sent to the steel yard is built this way, one bar mark at a time.

Task 2

Slab S3: bars, laps and mesh

Theory (9 min)
Rule
Count spaces, then add one. Lap once per joint. Cover comes off both ends of every bar.
How it is built
  • Bars across the slab = (Distance between first and last bar ÷ spacing, rounded up) + 1
  • Length of a mark 05 line = Slab length less cover + one lap
  • Mesh sheets = Sheets along the length × Sheets across the width
Usual mistake
One line is two bars lapped once, in the middle. The ends do not lap.
At work
Site engineers check the bar count of every slab before the concrete pour, against this same schedule.

Task 3

Weights, tonnage and the order

Theory (8 min)
Rule
The bill measures net steel; the order buys the waste too. Round each element, then multiply.
How it is built
  • Weight of one bar mark = Total length × Mass per metre, diameter² ÷ 162
  • Net tonnes of a size = Weight per element × Number of elements ÷ 1000
  • Order quantity = Net tonnes of each size × (1 + its waste) + the other sizes
Usual mistake
The bill measures net weight. Waste goes into the order and into the rate.
At work
Quantity surveyors bill net steel, and the site orders the same steel plus waste from the supplier.

Task 4

Price the reinforcement package

Theory (8 min)
Rule
Waste loads the supply price only. Labour is paid on the net tonne; the markup is one row.
How it is built
  • Rate of a size = Supply × (1 + waste) + Cut and bend + Fix
  • Package price = Rates × net tonnes + Overhead and profit
  • Average rate per net tonne = Grand total of the bill ÷ Sum of the net tonnes
Usual mistake
Waste loads the supply price only. Cutting and fixing are paid on the net tonne.
At work
Rebar subcontractors price every package like this: supply with waste, then cutting, bending and fixing.

Task 5

Revision C: re-measure the change

Theory (9 min)
Rule
A change of size comes out and goes in. New diameter, new cut length, then the bill rates and one markup.
How it is built
  • Net change of a size = Weight added − Weight omitted
  • Value of the change = Net tonnes × bill rate, each size + Overhead and profit
Usual mistake
The old bars come out of the structure. Omit them at the bill rates and add the new ones.
At work
Revised drawings arrive on every job; the QS re-measures the change and values it at bill rates.