Course introduction · 3 min

Developer cost check: can we pay the asking price? (UAE)

You are the cost manager of a Dubai developer. A landowner offers a plot for a ground-plus-twelve residential tower at AED 44 million and wants an answer at Thursday's board. In five tasks you build the case: the floor area, the contractor's price, the developer's cost limit, the funding the bank must provide, and the most the scheme can pay for the land.

Start task 1

A residential frame rising in Dubai: rebar bundles and cages in the yard, a tower crane and finished apartment blocks behind.Fictional project
Samar Heights, DubaiPlot offered at AED 44 million
Scheme
Ground plus twelve, one basement, apartments for sale off-plan
Stage
Feasibility: buy the plot or walk away
Method
RICS NRM1 order of cost estimate, then a residual land value
Work in the ERP
5 tasks, about 1 h 31 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • LandownerAsks AED 44 million
    • Asking priceTask 1
  • Sales teamPrices and escrow releases
    • GDV and cash inTask 4
YouDevelopment cost manager

Goes from you

    • Cost limitTask 3
    • ResidualTask 5
    BoardDecides go or no-go
    • Peak fundingTask 4
    BankLends against the peak

The project and the people are fictional. Portraits are generated.

Your route through the job

One feasibility appraisal, in the order a cost manager builds it. Task 1 is free: in the Bill of Quantities you measure the tower.

  1. Estimate

    Task 1 · 10 min

    The floor area the board will price

    You produce
    Gross internal floor area
    Document
    Order of cost estimate
    In the ERP
    Bill of Quantities
  2. Estimate

    Task 2 · 18 min

    What a contractor would charge to build it

    You produce
    Works cost estimate
    Document
    Order of cost estimate
    In the ERP
    Bill of Quantities
  3. Estimate

    Task 3 · 18 min

    The cost limit the board signs

    You produce
    Cost limit
    Document
    Board paper
    In the ERP
    Bill of Quantities
  4. Fund

    Task 4 · 25 min

    How deep the bank has to go

    You produce
    Peak funding and finance cost
    Document
    Development cashflow
    In the ERP
    Cost-Value Reconciliation
  5. Decide

    Task 5 · 20 min

    Go, no-go, or a counter-offer

    You produce
    Residual land value
    Document
    Board paper
    In the ERP
    Cost-Value Reconciliation

How one appraisal answers 'can we pay the asking price?'

Each step below is one task, in the order the appraisal is built.

Area
Task 1AreaEnclosed floor, balconies out.
ContractorWorks
Task 2Works costPreliminaries, then overheads and profit.
DeveloperWorks cost
Task 3Cost limitFees, other costs, risk last.
Peak
Task 4FundingThe deepest point and its interest.
LandGDV
Task 5ResidualWhat is left pays for the land.

Blue is what the task adds; grey is carried over from before.

In short. Price the enclosed floor, build costs in NRM1 order, fund the deepest point, and let the land take what is left.