Theory before task 1 · 7 min

Gross internal area: the area a cost rate is applied to

The floor area the board will price

Course introduction

After this lecture you can

  1. Say what gross internal area includes and leaves out.
  2. Measure a tower's gross internal area floor by floor.
  3. Apply the floor area method of an order of cost estimate.
1 / 3

Cost follows the enclosed floor

At feasibility there are no drawings to measure, only floor plates. A cost manager multiplies the gross internal area (GIA) by a cost per m2 from finished buildings of the same type. GIA is every enclosed floor measured to the inside face of the external walls: apartments, corridors, cores, plant rooms, the lift room on the roof.

Example. A ground-plus-eight block with 900 m2 floors and a 150 m2 roof plant room has a GIA of 9 × 900 + 150 = 8,250 m2.
AED7,200
  • Ground floor AED900
  • Typical floors AED7,200
  • Roof plant room AED150
2 / 3

Sellable is not buildable

Sales in Dubai are quoted per square foot of sellable area, which includes balconies. Cost is quoted per m2 of GIA, which does not. The two areas answer different questions and never replace each other in the same sum.

Example. Mixing them is how a tower gets priced on its brochure.
Common mistake

Pricing the balconies twice

Open balconies are outside the external wall. Their slab, balustrade and waterproofing are already in the benchmark rate, because the rate was taken from towers that had balconies. Adding their area applies the rate to them again.

Example. Check the rate's basis before you change the area it multiplies.

GIA of a smaller block

Different numbers from your task.

Not to scale
The problem
  • Ground floor 900 m2; 8 typical floors of 900 m2.
  • Each typical floor has 70 m2 of open balconies; roof plant room 150 m2.
Step 1 of 1

Enclosed floor

What is the gross internal area, in m2?

900 + 8 × 900 + 150 = 8,250.

In short. Inside the external walls, every level, plant included; balconies out.

Check yourself

Question 1 of 3

A covered, enclosed winter garden with full-height glazing in the external wall line. In GIA?

  • Right. Enclosure, not use, decides.

  • An enclosed space is floor area.

  • There is no half rule.

Question 2 of 3

Why not price the tower on its sellable area?

  • Right.

  • It is often smaller; the point is that it measures something else.

  • No regulator decides this; it is a matter of method.

Question 3 of 3

Ground 800 m2, ten typical floors of 760 m2, roof level 120 m2. GIA in m2?

800 + 7,600 + 120 = 8,520.