Theory before task 2 · 8 min

From the works to the works cost estimate

What a contractor would charge to build it

After this lecture you can

  1. Name the constituents of an NRM1 works cost estimate in order.
  2. Choose the base of each markup in the ERP.
  3. Keep recoverable VAT out of a developer's estimate.
1 / 3

Two layers on top of the works

The sum of the elements is what the work itself costs. A main contractor adds its preliminaries, the site set-up, management, cranes and welfare, as a share of the works. It then adds overheads and profit on works plus preliminaries, because it runs and finances both. In the ERP that is the Base of each markup row.

Example. Works AED 40 million, preliminaries 13 %, overheads and profit 5 % on the running total.
+AED40,000,0001+AED5,200,0002+AED2,260,0003AED47,460,0004
  • 1 Works
  • 2 Preliminaries
  • 3 Overheads and profit
  • 4 Works cost estimate
2 / 3

Why a developer's estimate is net of VAT

The contractor charges 5 % VAT on each invoice. The first sale of a new home in the UAE is zero-rated, so the developer can recover the VAT it paid on building it. Recovered VAT is a cash timing question, not a cost.

Example. A commercial scheme sold with VAT is different again; check the supply before you leave VAT out.
Common mistake

One flat percentage

Adding preliminaries and overheads and profit as one percentage of the works leaves the contractor without profit on its site set-up. The gap looks small and grows with every million of works.

Example. On AED 40 million, 18 % flat is AED 7,200,000; 13 % then 5 % on the running total is AED 7,460,000.

Works cost estimate of a smaller block

Different numbers from your task.

Not to scale
The problem
  • Sum of positions AED40,000,000.
  • Preliminaries 13% of the works; overheads and profit 5% of works plus preliminaries.
Step 1 of 2

Preliminaries

Works plus preliminaries?

AED40,000,000 × 1.13 = AED45,200,000.

Step 2 of 2

Overheads and profit

Works cost estimate?

AED45,200,000 × 1.05 = AED47,460,000.

In short. Preliminaries on the works; overheads and profit on both; VAT out.

Check yourself

Question 1 of 3

Which Base does overheads and profit need in the ERP?

  • Right, with preliminaries above it.

  • That leaves preliminaries without profit.

  • It is a percentage.

Question 2 of 3

A developer sells finished office floors with VAT. Is VAT in its cost estimate?

  • Right. Recoverable VAT is not cost either way.

  • Only unrecoverable VAT is cost.

  • VAT does not depend on the cost item.

Question 3 of 3

Works AED 20,000,000; preliminaries 10 %; overheads and profit 5 % on the running total. Works cost estimate?

20,000,000 × 1.10 × 1.05 = 23,100,000.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.