Two layers on top of the works
The sum of the elements is what the work itself costs. A main contractor adds its preliminaries, the site set-up, management, cranes and welfare, as a share of the works. It then adds overheads and profit on works plus preliminaries, because it runs and finances both. In the ERP that is the Base of each markup row.
- 1 Works
- 2 Preliminaries
- 3 Overheads and profit
- 4 Works cost estimate