The cost limit: what the developer, not the contractor, spends

The cost limit the board signs

After this lecture you can

  1. Add fees, other development costs and risk in NRM1 order.
  2. Choose a percentage or a fixed amount by how the cost behaves.
  3. Say what the cost limit includes and what it leaves out.
1 / 3

The developer's own costs

A contractor's price is only part of what the developer spends. Architects, engineers and the cost manager are paid fees, usually a share of the works cost estimate. Authority approvals and utility connections are quoted sums. Together they make the base cost estimate. A risk allowance on top of it covers what may still go wrong, and the total is the cost limit.

Example. Works cost estimate AED 47.5 million; fees 8 %; authority and connections AED 900,000; risk 6 %.
AED47,460,000
  • Works cost estimate AED47,460,000
  • Fees AED3,796,800
  • Other development costs AED900,000
  • Risk allowance AED3,129,408
2 / 3

Inflation is a separate decision

NRM1 adds inflation after the cost limit, from the estimate date to tender and through construction. This board prices inflation in its own model, so the cost limit here is at current prices.

Example. Write "excluding inflation" next to the figure every time it leaves your desk.
Common mistake

Risk on the contractor's price only

Fees and authority charges carry risk too: a redesign raises fees, a late connection raises charges. Risk on the works cost estimate alone leaves them bare. In the ERP the risk row goes last, on the running total.

Example. A fixed row below the risk row is not covered by it.

Cost limit of a smaller block

Different numbers from your task.

Not to scale
The problem
  • Works cost estimate AED47,460,000; fees 8%; other development costs AED900,000.
  • Risk allowance 6% of the base cost estimate.
Step 1 of 2

Base cost estimate

Base cost estimate?

AED47,460,000 × 1.08 + AED900,000 = AED52,156,800.

Step 2 of 2

Cost limit

Cost limit?

AED52,156,800 × 1.06 = AED55,286,208.

In short. Fees, then other costs, then risk on all of it; inflation and VAT outside.

Check yourself

Question 1 of 3

Where does the risk row go in the Markups list?

  • Right.

  • Then it misses everything above the works.

  • The ERP keeps your order.

Question 2 of 3

A DEWA connection is quoted at AED 600,000. How does it enter?

  • Right. A quote is a sum.

  • It does not grow with the works.

  • Connections are the developer's cost here.

Question 3 of 3

Base cost estimate AED 30,000,000; risk 5 %. Cost limit?

30,000,000 × 1.05 = 31,500,000.

Read the source