The developer's own costs
A contractor's price is only part of what the developer spends. Architects, engineers and the cost manager are paid fees, usually a share of the works cost estimate. Authority approvals and utility connections are quoted sums. Together they make the base cost estimate. A risk allowance on top of it covers what may still go wrong, and the total is the cost limit.
- Works cost estimate AED47,460,000
- Fees AED3,796,800
- Other development costs AED900,000
- Risk allowance AED3,129,408