Theory before task 4 · 9 min

Development cashflow: peak funding and finance cost

How deep the bank has to go

After this lecture you can

  1. Spread a cost limit over time and put land in at the start.
  2. Read escrow releases as the developer's cash in.
  3. Work out peak funding and simple finance cost.
1 / 3

Cash out first, cash in later

Land and its registration fee are paid at the start. Construction is spent along an S-curve. Buyers pay instalments from launch, but the money sits in the project's escrow account and reaches the developer as construction progresses. The deepest point of the cumulative net is what the bank has to fund.

Example. A scheme with AED 30 million of land up front and slow early sales is most in debt halfway through construction.
Half-year 1
AED34,000,000
Half-year 2
AED41,000,000
Half-year 3
AED44,000,000
Half-year 4
AED36,000,000
2 / 3

Finance in this case

The bank charges a half-year rate on each negative closing balance. Interest is worked out beside the cashflow and not added to it, which is a simplification the board accepts at feasibility.

Example. Closing balances −30, −40 and −20 million at 3 % per half-year cost 2.7 million.
Common mistake

The peak for the whole period

Charging interest on the peak balance for every half-year assumes the debt is at its deepest all the time. It overstates finance and understates what the land is worth.

Example. Each half-year carries its own balance.

Finance on a smaller scheme

Different numbers from your task.

Not to scale
The problem
  • Closing cumulative net: −AED30,000,000, −AED40,000,000, −AED20,000,000, then positive.
  • Interest 3% per half-year on each negative balance.
Step 1 of 1

Interest

Finance cost?

(AED30,000,000 + AED40,000,000 + AED20,000,000) × 3 % = AED2,700,000.

In short. Peak funding is the lowest cumulative net; finance is the rate on each negative balance.

Check yourself

Question 1 of 3

Which ERP figure is the peak funding?

  • Right.

  • That is spending, not debt.

  • That is the surplus at completion.

Question 2 of 3

Why is the 4 % fee in the first half-year?

  • Right.

  • It comes with the land.

  • Here it is the developer's purchase of the plot.

Question 3 of 3

Closing balances −10, −25 and −5 million; 4 % per half-year. Finance cost?

40,000,000 × 4 % = 1,600,000.

Read the source