Cheat sheet

Measure to IS 1200 and bill it (India)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Measure the brickwork: which openings come out

Theory (10 min)
Rule
IS 1200 (Part III): an opening up to 0.1 m² is not deducted from brickwork. Lintels are paid on the RCC line.
How it is built
  • Net area = Length × height − openings over the threshold only
  • Brickwork volume = Net area × wall thickness − RCC lintels
Usual mistake
IS 1200 (Part III)-1976, cl. 4.1.4(b): an opening up to 0.1 m² is not deducted. N1 is 0.09 m² and S1 is 0.04 m².
At work
Junior engineers measure walls like this in the measurement book, and the Engineer-in-Charge checks them before any bill is paid.

Task 2

Plaster on the same wall: three thresholds, not one

Theory (11 min)
Rule
IS 1200 (Part XII): three size bands. Reveals are added only for an opening over 3 m².
How it is built
  • Openings deducted = Middle band: one face each + Over the upper band: both faces
  • Plaster area = Both faces − Openings deducted + Reveals of the large opening
  • Brickwork still on its line = Line 2.3 quantity
Usual mistake
For an opening over 0.5 m² and up to 3 m² with the same plaster on both faces, only one face is deducted. Both faces come off only above 3 m².
At work
Every finishing bill on a CPWD-style job is measured to these bands, opening by opening.

Task 3

Price the abstract: base rates, cost index, tender percentage

Theory (10 min)
Rule
Index first, tender percentage second: the 6.42 % is taken on the total after the 12 %, not on the base total.
How it is built
  • Section 2 at base rates = Quantity × base rate, each line + Line 2.3 rate × its quantity
  • Value at estimate rates = Base total + Cost index on it
  • Gross value = Value at estimate rates + Tender percentage on it
Usual mistake
Both additions are there, but the tender percentage was taken on the base total instead of the indexed total.
At work
Contractors on government work price every bill from the schedule, the notified cost index and their own quoted percentage.

Task 4

Running account bill 1 in the ERP

Theory (9 min)
Rule
The claim re-keys the abstract: three sections at base rates, then the cost index, then the tender percentage.
How it is built
  • Gross of the bill = Section 2 line + Sections 1 and 3 + Cost index line + Tender percentage line
  • Share billed = Gross ÷ Tendered amount × 100
  • Still to bill = Tendered amount − Gross
Usual mistake
Measure the bill against the tendered amount, the figure the contract is for, not against the estimated cost put to tender.
At work
Each month the contractor's billing engineer raises the running bill, and the Engineer-in-Charge checks it against the measurement book.

Task 5

Recoveries: security deposit, welfare cess, GST

Theory (11 min)
Rule
Tendered rates include GST, so the tax is divided out. The deposit is on the gross; cess and tax at source are on the value without GST.
How it is built
  • Taxable value = Gross ÷ (1 + GST rate)
  • Due after the deposit = Gross − Security deposit
  • Amount payable = Due after the deposit − Cess on taxable value − GST TDS on taxable value
Usual mistake
That is the figure after the security deposit only. The welfare cess and the tax deducted at source still come off.
At work
Divisional accounts deduct these three on every running bill, and contractors reconcile them each month.