Cheat sheet
Measure to IS 1200 and bill it (India)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- IS 1200 (Part III): an opening up to 0.1 m² is not deducted from brickwork. Lintels are paid on the RCC line.
- How it is built
- Net area = Length × height − openings over the threshold only
- Brickwork volume = Net area × wall thickness − RCC lintels
- Usual mistake
- IS 1200 (Part III)-1976, cl. 4.1.4(b): an opening up to 0.1 m² is not deducted. N1 is 0.09 m² and S1 is 0.04 m².
- At work
- Junior engineers measure walls like this in the measurement book, and the Engineer-in-Charge checks them before any bill is paid.
- Rule
- IS 1200 (Part XII): three size bands. Reveals are added only for an opening over 3 m².
- How it is built
- Openings deducted = Middle band: one face each + Over the upper band: both faces
- Plaster area = Both faces − Openings deducted + Reveals of the large opening
- Brickwork still on its line = Line 2.3 quantity
- Usual mistake
- For an opening over 0.5 m² and up to 3 m² with the same plaster on both faces, only one face is deducted. Both faces come off only above 3 m².
- At work
- Every finishing bill on a CPWD-style job is measured to these bands, opening by opening.
- Rule
- Index first, tender percentage second: the 6.42 % is taken on the total after the 12 %, not on the base total.
- How it is built
- Section 2 at base rates = Quantity × base rate, each line + Line 2.3 rate × its quantity
- Value at estimate rates = Base total + Cost index on it
- Gross value = Value at estimate rates + Tender percentage on it
- Usual mistake
- Both additions are there, but the tender percentage was taken on the base total instead of the indexed total.
- At work
- Contractors on government work price every bill from the schedule, the notified cost index and their own quoted percentage.
- Rule
- The claim re-keys the abstract: three sections at base rates, then the cost index, then the tender percentage.
- How it is built
- Gross of the bill = Section 2 line + Sections 1 and 3 + Cost index line + Tender percentage line
- Share billed = Gross ÷ Tendered amount × 100
- Still to bill = Tendered amount − Gross
- Usual mistake
- Measure the bill against the tendered amount, the figure the contract is for, not against the estimated cost put to tender.
- At work
- Each month the contractor's billing engineer raises the running bill, and the Engineer-in-Charge checks it against the measurement book.
- Rule
- Tendered rates include GST, so the tax is divided out. The deposit is on the gross; cess and tax at source are on the value without GST.
- How it is built
- Taxable value = Gross ÷ (1 + GST rate)
- Due after the deposit = Gross − Security deposit
- Amount payable = Due after the deposit − Cess on taxable value − GST TDS on taxable value
- Usual mistake
- That is the figure after the security deposit only. The welfare cess and the tax deducted at source still come off.
- At work
- Divisional accounts deduct these three on every running bill, and contractors reconcile them each month.