Course introduction · 3 min
Unit rate build-up: labour, materials, plant, variation
You are the main contractor's estimator on a six-storey mixed-use building under the FIDIC Red Book. The tender closes on 5 March at 12:00 and three items of the bill still have no rate. In five tasks you build them from labour, materials and plant, then price an instructed change in November with the same build-up.
Fictional project- Works
- Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame.
- Contract
- FIDIC Red Book 2017, remeasurement, net bill rates
- Method
- Unit rates from labour, materials and plant
- Work in the ERP
- 5 tasks, about 1 h 22 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site managerGang outputs from records
- OutputsTask 1
- SuppliersMaterial and plant prices
- PricesTask 2
- The EngineerInstructs the change
- EI-14Task 4
Goes from you
- RatesTask 3
- Cost impactTask 5
Your route through the job
Three rates for the tender, then one change during the works. Every task is free.
Tender
Task 1 · 12 min
Labour per m2 from the gang
- You produce
- Labour from the gang
- Document
- Tender bill
- In the ERP
- Bill of Quantities
Tender
Task 2 · 15 min
Two layers each side, plus waste
- You produce
- Materials with waste
- Document
- Tender bill
- In the ERP
- Bill of Quantities
Tender
Task 3 · 15 min
The pump charges by the hour
- You produce
- Plant by output
- Document
- Tender bill
- In the ERP
- Bill of Quantities
Variation
Task 4 · 20 min
A changed wall needs a new rate
- You produce
- New rate for a changed wall
- Document
- Tender bill
- In the ERP
- Bill of Quantities
Variation
Task 5 · 20 min
Price the change, not the new wall
- You produce
- Variation cost impact
- Document
- Variation request
- In the ERP
- Variations
How a unit rate is built
Each step below is one task, in the order an estimator meets them.
Blue is what the task adds; grey is carried over from before.
In short. Build every rate from what the work uses, price each resource in its own unit, and value a change from the same build-up.