Course introduction · 3 min

Unit rate build-up: labour, materials, plant, variation

You are the main contractor's estimator on a six-storey mixed-use building under the FIDIC Red Book. The tender closes on 5 March at 12:00 and three items of the bill still have no rate. In five tasks you build them from labour, materials and plant, then price an instructed change in November with the same build-up.

Start task 1

A concrete frame of six storeys with a tower crane and blank hoardings, on a clear day.Fictional project
Mixed-use building, 6 storeysConcrete frame going up
Works
Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame.
Contract
FIDIC Red Book 2017, remeasurement, net bill rates
Method
Unit rates from labour, materials and plant
Work in the ERP
5 tasks, about 1 h 22 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site managerGang outputs from records
    • OutputsTask 1
  • SuppliersMaterial and plant prices
    • PricesTask 2
  • The EngineerInstructs the change
    • EI-14Task 4
YouEstimator

Goes from you

    • RatesTask 3
    Tender sheetNet rates
    • Cost impactTask 5
    Contractor's quantity surveyorVariation proposal

Your route through the job

Three rates for the tender, then one change during the works. Every task is free.

  1. Tender

    Task 1 · 12 min

    Labour per m2 from the gang

    You produce
    Labour from the gang
    Document
    Tender bill
    In the ERP
    Bill of Quantities
  2. Tender

    Task 2 · 15 min

    Two layers each side, plus waste

    You produce
    Materials with waste
    Document
    Tender bill
    In the ERP
    Bill of Quantities
  3. Tender

    Task 3 · 15 min

    The pump charges by the hour

    You produce
    Plant by output
    Document
    Tender bill
    In the ERP
    Bill of Quantities
  4. Variation

    Task 4 · 20 min

    A changed wall needs a new rate

    You produce
    New rate for a changed wall
    Document
    Tender bill
    In the ERP
    Bill of Quantities
  5. Variation

    Task 5 · 20 min

    Price the change, not the new wall

    You produce
    Variation cost impact
    Document
    Variation request
    In the ERP
    Variations

How a unit rate is built

Each step below is one task, in the order an estimator meets them.

Labour
Task 1LabourGang-day ÷ output.
Materials
Task 2MaterialsCount, price, waste.
Plant
Task 3PlantHire ÷ output.
Build-up
Task 4New rateChange the changed parts.
OH PNet
Task 5VariationOmit, add, mark up.

Blue is what the task adds; grey is carried over from before.

In short. Build every rate from what the work uses, price each resource in its own unit, and value a change from the same build-up.