All 5 tasks freeFoundation1.5 h of studyInternational

Unit rate build-up: labour, materials, plant, variation

On a fictional six-storey mixed-use building under the FIDIC Red Book.

Who it's for Main contractor's estimator (net unit rates, FIDIC Red Book 2017)

Workspace: Unit rate build-up: labour, materials, plant, variation
Build up a unit rate

You will be able to

Skills checked

  • Build labour per unit from a gang's all-in rates and its recorded output
  • Price materials per unit from the specification, with waste only on what is cut
  • Turn hourly plant hire into a cost per unit from the plant's output
  • Derive a new rate for a changed item from the bill's own build-up (FIDIC 12.3)
  • Value a variation as added less omitted work, add overheads and profit, and submit it

Tasks

A task as it opens in the trainer, before you enter anything.

Task 1 as it opens in the trainer: Labour per m2 from the gang
  1. 1
    Labour per m2 from the gang≈12 minTheory · 6 min
  2. 2
    Two layers each side, plus waste≈15 minTheory · 7 min
  3. 3
    The pump charges by the hour≈15 minTheory · 6 min
  4. 4
    A changed wall needs a new rate≈20 minTheory · 7 min
  5. 5
    Price the change, not the new wall≈20 minChangeTheory · 7 minCheat sheet: every rule on one page

Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.

Videos on this method

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks.

Certificates

Sample: Certificate of completion
Sample issued to a fictitious learner. Your certificate shows your name, the course, the date and its own ID.
Check this sample

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • Estimatebill of quantities14 lines
  • parties3 records

Start free course All courses

What next

When you pass, add the certificate to LinkedIn from your account. Anyone can open its verification link, no sign-in needed. How to add it

Questions about this course? Write to info@datadrivenconstruction.io

Related courses

Start free: task 1 of 5All 5 tasks free · 1.5 h of study

Start free course