Unit rate build-up: labour, materials, plant, variation
On a fictional six-storey mixed-use building under the FIDIC Red Book.
Who it's for Main contractor's estimator (net unit rates, FIDIC Red Book 2017)

You will be able to
Skills checked
- Build labour per unit from a gang's all-in rates and its recorded output
- Price materials per unit from the specification, with waste only on what is cut
- Turn hourly plant hire into a cost per unit from the plant's output
- Derive a new rate for a changed item from the bill's own build-up (FIDIC 12.3)
- Value a variation as added less omitted work, add overheads and profit, and submit it
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Videos on this method
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks.

Files you work with
Created in your OpenConstructionERP workspace the moment you enrol.
- Estimatebill of quantities14 lines
- parties3 records
What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses
Your roleEstimatorTender estimate: from net rates to the tender sum
On a fictional six-storey mixed-use building.
Foundation1 h of studyFigures checked 10EN
All 5 tasks freeCertificate of completion
Your roleQuantity surveyor at the client's cost consultantQuantity takeoff from PDF, DWG and IFC
On an invented six-storey mixed-use building.
Foundation1.5 h of studyFigures checked 13EN
All 5 tasks freeCertificate of completion

Your roleContractor's quantity surveyor
Price, win and vary a FIDIC contract
Take one building from tender to its first variation under the FIDIC Red Book 2017: price the last blank lines, build the tender sum, level and award the drywall.
Foundation1.5 h of studyFigures checked 21EN
All 5 tasks freeCertificate of completion