Theory before task 4 · 7 min

A new rate from the bill's own build-up

A changed wall needs a new rate

After this lecture you can

  1. Say when FIDIC 12.3 calls for a new rate.
  2. Change only the parts of the build-up that the instruction changes.
  3. Record a new rate as its own bill position.
1 / 3

Similar or not

Work like the bill's item, under similar conditions, is valued at the bill rate. Work of a different character gets a new rate, and FIDIC asks that it be derived from the rates in the Contract, with reasonable adjustment. The build-up is how you show that.

Example. Moving a partition along the same floor: same character, same rate. Adding a layer: a different item.
Same parts
USD3
Changed parts
USD2
2 / 3

Change the changed parts

Copy the bill item's build-up. Change the quantities the instruction changes, add the labour that goes with them, keep the rest. The Engineer can then check each change against the tender.

Example. A ceiling gets a second layer of board: board doubles, fixing time rises; the grid and the hangers stay.
Common mistake

Scaling the whole rate

Six boards are 50 % more than four, but the studs and the jointing are the same wall. Scaling the whole rate by 1.5 charges for studs and joints nobody adds.

Example. Scale parts, never the whole rate.

A ceiling with a second layer

Different numbers from your task.

Not to scale
The problem
  • Bill item per m2: grid USD8.00, one layer of board USD4.50, labour USD10.00.
  • Second layer: one more board, 2.00 more labour.
Step 1 of 2

Bill rate

Bill rate per m2?

USD8.00 + USD4.50 + USD10.00 = USD22.50.

Step 2 of 2

New rate

New rate per m2?

USD8.00 + 2 × USD4.50 + USD10.00 + 2.00 = USD29.00.

In short. Copy the build-up, change what the instruction changes, keep the rest.

Check yourself

Question 1 of 3

The partition moves 2 m along the same floor. New rate?

  • Right.

  • Only work that differs.

  • That is not a FIDIC default.

Question 2 of 3

What does the Engineer check first in a new rate?

  • Right. FIDIC 12.3.

  • It can be higher.

  • The Contract's rates come first.

Question 3 of 3

Bill rate 32.00 = 12.00 labour + 20.00 materials. The change doubles the materials only. New rate?

12.00 + 2 × 20.00 = 52.00.