Theory before task 5 · 7 min

Valuing a variation: omit, add, then overheads and profit

Price the change, not the new wall

After this lecture you can

  1. Value a changed item as the new work less the work it replaces.
  2. Apply the Contract Data's mark-ups on the net change, in order.
  3. Submit the proposal in Variations.
1 / 3

The change, not the new wall

When an instruction replaces work that is in the bill, the replaced work is omitted at the bill rate and the new work added at its rate. The variation is the difference. Pricing only the new work charges the Employer twice for the same m2.

Example. Swap 50 m2 of tiles at 40.00 for 50 m2 at 55.00: the change is 750.00, not 2,750.00.
+USD2,7501−USD2,0002USD7503
  • 1 Added
  • 2 Omitted
  • 3 Net change
2 / 3

Mark-ups in the order of the Contract Data

Net bill rates carry no overheads or profit, so the variation needs them added, as the tender did. Each goes on the running total. The Contract Data of this case leaves the tender risk allowance off instructed work.

Example. Net change 1,000.00, overheads 5 % then profit 4 %: 1,050.00, then 1,092.00.
Common mistake

One percentage for both

Adding the percentages first and applying them once leaves out the profit on the overheads. On a large final account the gap is real money.

Example. Apply each mark-up on the total before it.

A tile change

Different numbers from your task.

Not to scale
The problem
  • Added USD2,750.00; omitted USD2,000.00.
  • Overheads 5 %, then profit 4 %, each on the running total.
Step 1 of 2

Net

Net change?

USD2,750.00 − USD2,000.00 = USD750.00.

Step 2 of 2

Impact

Cost impact?

USD750.00 × 1.05 × 1.04 = USD819.00.

In short. New work less replaced work, then each mark-up on the running total.

Check yourself

Question 1 of 3

An instruction adds work that was nowhere in the bill. What is omitted?

  • Right.

  • Nothing was replaced.

  • Only if the instruction says so.

Question 2 of 3

Who agrees the valuation under FIDIC?

  • Right. 13.3.1 and 3.7.

  • It proposes.

  • Not a party to valuation.

Question 3 of 3

Net change 2,000.00; overheads 6 % then profit 5 %, each on the running total. Cost impact?

2,000.00 × 1.06 × 1.05 = 2,226.00.