The change, not the new wall
When an instruction replaces work that is in the bill, the replaced work is omitted at the bill rate and the new work added at its rate. The variation is the difference. Pricing only the new work charges the Employer twice for the same m2.
- 1 Added
- 2 Omitted
- 3 Net change