Theory before task 3 · 6 min

Plant: from a rate per hour to a cost per unit

The pump charges by the hour

After this lecture you can

  1. Turn a hire rate per hour into a cost per unit with the plant's output.
  2. Keep small plant recorded per unit as it is.
  3. Check the division by its units.
1 / 3

Hired by time, billed by quantity

A pump, a crane hour or a dumper is hired by the hour or the day. The bill pays per m3 or m2. The plant cost per unit is the hire for a period divided by what the plant produces in that period.

Example. An excavator at 90.00 an hour digging 45 m3 an hour costs 2.00 per m3.
USD90USD30
  • Hire per hour USD90
  • ÷ output per hour USD30
2 / 3

Units tell you if it is right

USD per hour ÷ m3 per hour = USD per m3. If the units come out as m3 per USD or USD × m3, the division is the wrong way round. Small plant recorded per unit, like vibrators per m3, is added as it is.

Example. A mixer recorded at 0.60 per m2 of wall needs no division.
Common mistake

The hour as the unit

Putting the hourly hire straight into a rate per m3 makes the plant thirty times too dear on a pump that places thirty m3 an hour. The tender loses on price and nobody notices until the tender is lost.

Example. Write the units next to every figure.

Plant per m3 for an excavation

Different numbers from your task.

Not to scale
The problem
  • Excavator with driver USD90.00 an hour.
  • Output 45 m3 an hour; dumper recorded at 1.10 per m3.
Step 1 of 2

Excavator

Excavator per m3?

USD90.00 ÷ 45 = USD2.00.

Step 2 of 2

Plant

Plant per m3?

USD2.00 + 1.10 = USD3.10.

In short. Hire ÷ output for time-hired plant; per-unit plant as recorded.

Check yourself

Question 1 of 3

A crane costs 120 an hour and lifts 8 m2 of panel an hour. Crane per m2?

  • Right.

  • That multiplies.

  • That divides the wrong way round.

Question 2 of 3

Which plant needs dividing by an output?

  • Right.

  • That is already per unit.

  • Only what is hired by time.

Question 3 of 3

Pump 150 an hour, 25 m3 an hour. Pump per m3?

150 ÷ 25 = 6.00.