One m2 of the item is not one m2 of each material
The bill measures the item: one m2 of wall. The supplier prices the material: one m2 of board, one m of track. Read the specification and count how much of each material one unit of the item takes.
Theory before task 2 · 7 min
Two layers each side, plus waste
The bill measures the item: one m2 of wall. The supplier prices the material: one m2 of board, one m of track. Read the specification and count how much of each material one unit of the item takes.
Board, studs and blocks are cut to fit; offcuts and breakage are lost. A waste factor adds them: quantity × price × (1 + waste). Materials priced per unit of work done, like jointing per m2, carry no waste of their own.
The description says the layers, but the price is for one. Reading two layers each side as two m2 halves the board; reading it as eight doubles it.
Different numbers from your task.
Board per m2 of wall?
Hint: Two faces, one layer each.
Materials per m2 of wall?
Hint: Add the framing with its own waste.
Right.
Labour is not wasted material.
A price per m2 is for the m2 delivered.
Right.
That is one face.
That counts each layer twice.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
Sub-Clause 4.11: the rate must cover the whole specification, every layer included.
Materials as a direct resource of the item, priced at the cost delivered to site.