Cheat sheet
Unit rate build-up: labour, materials, plant, variation
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The gang builds the wall. Cost the whole gang for a day, divide by what it builds that day.
- How it is built
- Labour per m2 = Gang-day cost ÷ Output per day
- Usual mistake
- Only the masons were costed. The operative is part of the gang that builds the 20 m2: add his day.
- At work
- Estimators keep gang outputs from past jobs and price labour from them, trade by trade.
- Rule
- Count the layers, then add the waste. Two layers each side is four m2 of board; waste only on what is cut.
- How it is built
- Materials per m2 = Studs × 1.05 + 4 boards × 1.08 + Jointing
- Usual mistake
- Only one face was boarded. Two layers each side is four m2 of board per m2 of wall.
- At work
- The estimator reads the specification line by line and sketches the section before pricing.
- Rule
- Hired by the hour, billed by the m3. Hire per hour ÷ m3 per hour; small plant per m3 as recorded.
- How it is built
- Plant per m3 = Pump hire ÷ Output + Vibrators
- Usual mistake
- The pump's hourly rate went in as a cost per m3. Divide it by the 30 m3 it places in that hour.
- At work
- Plant quotes come per hour or per day; the estimator converts them with the output on this job.
- Rule
- Change the changed parts. Start from INT.01's build-up; more board and more fixing, the rest as it was.
- How it is built
- New rate = Studs + 6 boards + Jointing + Fixing time
- Usual mistake
- The whole rate was scaled by 6 ÷ 4. Studs and jointing do not change; price only the extra board and its fixing.
- At work
- Commercial teams price changes by copying the tender build-up and showing each changed part.
- Rule
- Price the change, not the new wall. Added less omitted, then overheads, then profit; no risk allowance.
- How it is built
- Cost impact = Added − Omitted × 1.06 × 1.05
- Usual mistake
- The new wall was priced in full. 120 m2 of INT.01 are no longer built: omit them at the bill rate first.
- At work
- The QS sends the Engineer the omit, the add and the mark-ups, each traceable to the bill.