OpenConstruction Academy
Sign in / Register
EN

Theory before task 4 · 12 min

Building a progress claim: to date, less certified, plus GST

Payment claim 7 for the named month

After this lecture you can

  1. Value each trade to date, by percentage or by remeasure as the contract says.
  2. Turn values to date into this claim by taking off what earlier claims certified.
  3. Add completed variations and put GST on once, at the foot.
1 / 3

Every trade to date

AS 4000 has the contractor claim payment progressively for work done. The claim is built on the schedule of values: the contract sum split into trades. Each trade is valued for everything done since the start of the job. Most trades are a percentage of their contract value. A remeasured trade carries its bill value to date instead.

Example. Dark: done to date. Hatched: still to build.
Preliminaries, 45 %
$320,000 ($144,000 + $176,000)
Frame, remeasured
$710,000 ($238,470 + $471,530)
Roofing, 25 %
$480,000 ($120,000 + $360,000)
2 / 3

This claim is the movement

A claim asks for what is not yet certified. For each trade, take the value to date and subtract what earlier claims certified for it. A trade finished last month moves by nothing. A completed variation is added as its own line at its full value, because nothing of it was certified before.

Example. A claim that carries values to date on every line claims the earlier months again.
Preliminaries, to date$144,000
Certified in earlier claims$112,000
This claim$32,000
3 / 3

GST at the foot, once

Bill rates, trade values and variations are all excluding GST. The claim totals them, then adds GST of one tenth on that total, once. A payment claim under the NSW Security of Payment Act states the amount claimed, so the figure served is the total including GST.

Example. GST on each line and again on the total is the most common double count.
$182,4001+$5,6002+$18,8003$206,8004
  • 1 Trades, this claim
  • 2 Variation
  • 3 GST, one tenth
  • 4 Total claimed

Build a claim

Another job, claim 5. Three trades have started; the rest stand at zero.

Not to scale
The problem
  • Preliminaries: contract value $325,000, 62% complete, certified $165,750.00.
  • Frame, remeasured: $288,412.60 at bill rates to date, certified $201,880.35.
  • Roofing: contract value $410,000, 35% complete, certified $71,750.00.
  • Variation 9, complete: $6,284.75. GST one tenth.
To date$201,500.00
Certified$165,750.00
This claim?
To date$201,500.00
Certified$165,750.00
This claim$35,750.00
Step 1 of 4

Preliminaries line

Value to date less certified. What does the preliminaries line claim?

$325,000 × 62% = $201,500.00 to date. Less $165,750.00: $35,750.00.

Preliminaries
$201,500
Frame
$288,413
Roofing
$143,500
Preliminaries
$201,500
Frame
$288,413
Roofing
$143,500
Step 2 of 4

Trades to date

Add the three trades to date. What is the work completed to date?

Preliminaries, frame and roofing to date: $633,412.60.

$633,4131−$439,3802+$6,2853?4
  • 1 To date
  • 2 Certified before
  • 3 Variation 9
  • 4 Claim 5
$633,4131−$439,3802+$6,2853$200,3174
  • 1 To date
  • 2 Certified before
  • 3 Variation 9
  • 4 Claim 5
Step 3 of 4

Claim excluding GST

Take off what was certified and add variation 9. What is claim 5 excluding GST?

$633,412.60 less $439,380.35 certified, plus $6,284.75: $200,317.00.

$200,317?
  • Excluding GST $200,317
  • GST ?
$200,317
  • Excluding GST $200,317
  • GST $20,032
Step 4 of 4

Total claimed

Add GST at one tenth. What is the total claimed?

$200,317.00 plus GST is $220,348.70.

In short. Value to date, less certified, plus variations, then GST once.

Check yourself

Question 1 of 3

A trade was finished and fully certified in claim 4. What does it carry in claim 5?

  • That claims it a second time.

  • Value to date less certified is zero.

  • Retention is released under the security terms, not as a trade line.

  • GST follows the value claimed, which is zero.

Question 2 of 3

Where does GST belong in a payment claim?

  • Lines stay excluding GST, or the tax is counted line by line and again at the foot.

  • One tenth of the claimed value, added at the foot.

  • All taxable work carries GST, not only variations.

  • The claim states the amount claimed, tax included.

Question 3 of 3

A trade worth $520,000 is 65 % complete. Earlier claims certified $234,000 for it. What does this claim carry for it, excluding GST?

$520,000.00 × 0.65 = $338,000.00. Less $234,000.00 = $104,000.00.