One course task, step by step

Read a short lecture, then do the work in the real ERP. Every figure you enter is checked and explained.

Example from the course Tender to first valuation (UK, JCT)

  1. Learn the method

    A worked example: you predict the figure, then see how it is built

    A worked example: you predict the figure, then see how it is built

  2. Do the task in the ERP

    Task 1: Price the dry lining package

    Task 1: Price the dry lining package

  3. Every figure is checked

    The check: which figures match, and which mistake you made

    The check: which figures match, and which mistake you made

Fictional project
Tallowgate WorksFour-storey office · tender stage

A case in the style of the free course Tender to first valuation (UK, JCT)

Which subcontractor is really cheaper?

You are the estimator at the , the firm bidding to build this office. Today you choose who builds the fire-rated partitions. Two sent , and one is much cheaper.

3 decisions · about 4 minutes · no account needed

Step 1 of 3

Read the quote against the spec

Tick each exclusion that leaves a hole in your price: the spec asks for that work and nobody else is paying for it.

SpecificationClause 20.4 · Fire-rated partition P2
  1. 20.4.1Metal stud partition, two layers of 15 mm fire board on each side, 60 minutes fire resistance.
  2. 20.4.2Cavity filled with 50 mm , no gaps.
  3. 20.4.3Head of partition sealed to the underside of the floor above with tested .
  4. 20.4.4Joints taped and filled, ready for paint.

A.3General clause: the main contractor provides access towers for all trades.

Quote · Sub AFire-rated partition P2
QuantityAmount
Partition P2, materials and fixing636 m²£46.00£29,256.00

Includes: studs, boards, fixing, taping and filling.

: