One course task, step by step
Read a short lecture, then do the work in the real ERP. Every figure you enter is checked and explained.
Example from the course Tender to first valuation (UK, JCT)

A case in the style of the free course Tender to first valuation (UK, JCT)
Which subcontractor is really cheaper?
You are the estimator at the , the firm bidding to build this office. Today you choose who builds the fire-rated partitions. Two sent , and one is much cheaper.
Step 1 of 3
Read the quote against the spec
Step 2 of 3
Price the gap
Step 3 of 3
Level the quotes and decide
What you just learned
- A quote is as cheap as its scope. Read it against the spec, exclusion by exclusion, before you compare prices.
- Waste goes in the rate. The measured quantity stays net, so the bill can be re-measured and still add up.
- Known costs go in the price. The risk allowance is only for what might happen, and mark-ups go on once, at the end.
5 tasks in the real bill, every figure checked like this one. About the course
In the course you build a whole tender in OpenConstructionERP: you enter the rates into the bill, level real quotes, and every figure is checked against a worked solution.