Course introduction · 3 min

AI-generated programme, verified (Brazil)

You are the builder's planner on a school extension in Brazil, a public job. The programme is the timetable of the work: what is done when, and how long each part takes. Your firm's AI assistant has drafted it. In six tasks, in the Schedule module, you check its durations and its links, read the critical path (the chain of work that sets the finish) against the contract term, then measure progress and plan cash from the corrected programme.

Start task 1

A school extension under construction in Brazil.Fictional project
Serra Clara school extensionMunicipal school · public works, unit prices
Contract
Public works paid at unit prices, under Law 14.133/2021
Calendar
Monday to Friday, 8 h a day
Starting point
An AI baseline programme, unchecked
Work in the ERP
6 tasks, about 3 h 15 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • AI assistantDrafted the programme
    • DurationsTask 1
    • LogicTask 3
    • 'It fits the term'Task 4
    • Progress by timeTask 5
    • Even S-curveTask 6
  • Contract inspector (fiscal)Measures the work
    • MeasurementTask 5
YouPlanner, contractor

Goes from you

    • Baseline programmeTask 4
    • Physical-financial scheduleTask 6
    MunicipalityThe buyer

The project and the people are fictional. Portraits are generated.

Your route through the job

First make the programme right, then use it to measure progress and plan cash. Start with task 1: in Schedule you work out the blockwork duration from the hours per unit in its cost composition.

  1. Programme

    Task 1 · 15 min

    The blockwork duration from the composição

    You produce
    The blockwork duration from its unit composition
    Document
    Unit cost compositions (hours of each trade per unit) and crews
    In the ERP
    Schedule
  2. Programme

    Task 2 · 30 min

    The full programme: render, painting and the draft's logic

    You produce
    The full programme: all twelve activities with the draft's links
    Document
    AI draft: activities, durations and logic
    In the ERP
    Schedule
  3. Programme

    Task 3 · 40 min

    Invented links: the logic the AI made up

    You produce
    Links between tasks, without invented ones
    Document
    Design construction sequence
    In the ERP
    Schedule
  4. Programme

    Task 4 · 35 min

    Critical path and finish: does it fit the period?

    You produce
    Critical path, planned duration, and the margin to the contract term
    Document
    Contract calendar
    In the ERP
    Schedule
  5. Progress and cash

    Task 5 · 35 min

    Physical progress: measured, not assumed

    You produce
    Planned value, earned value (the value of the work done) and physical progress
    Document
    Inspector's measurement
    In the ERP
    Earned value
  6. Progress and cash

    Task 6 · 40 min

    S-curve and cash: the physical-financial programme

    You produce
    S-curve and monthly cash
    Document
    Payment terms of the contract
    In the ERP
    Cost and cash

From a draft programme to a cash plan

Each step below is one task. Every later figure depends on the programme being right first.

Durations
Task 1DurationsQuantity times the hours per unit, shared over the crew.
Logic, critical pathDurations
Task 3Logic and pathKeep only links with a building reason; the longest chain sets the finish.
Earned valueLogicDurations
Task 4ProgressMeasured on site, compared with the plan.
Cash planCorrected programme
Task 5CashSpent in the month the work is done, paid the month after.

Blue is what the task adds; grey is carried over from before.

In short. Compute durations from productivity, keep only links with a construction reason, read the longest path, and measure progress rather than assume it.