Course introduction · 3 min
AI-generated programme, verified (Brazil)
You are the builder's planner on a school extension in Brazil, a public job. The programme is the timetable of the work: what is done when, and how long each part takes. Your firm's AI assistant has drafted it. In six tasks, in the Schedule module, you check its durations and its links, read the critical path (the chain of work that sets the finish) against the contract term, then measure progress and plan cash from the corrected programme.
Fictional project- Contract
- Public works paid at unit prices, under Law 14.133/2021
- Calendar
- Monday to Friday, 8 h a day
- Starting point
- An AI baseline programme, unchecked
- Work in the ERP
- 6 tasks, about 3 h 15 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- AI assistantDrafted the programme
- DurationsTask 1
- LogicTask 3
- 'It fits the term'Task 4
- Progress by timeTask 5
- Even S-curveTask 6
- Contract inspector (fiscal)Measures the work
- MeasurementTask 5
YouPlanner, contractorGoes from you
- Baseline programmeTask 4
- Physical-financial scheduleTask 6
The project and the people are fictional. Portraits are generated.
Your route through the job
First make the programme right, then use it to measure progress and plan cash. Start with task 1: in Schedule you work out the blockwork duration from the hours per unit in its cost composition.
Programme
Task 1 · 15 min
The blockwork duration from the composição
- You produce
- The blockwork duration from its unit composition
- Document
- Unit cost compositions (hours of each trade per unit) and crews
- In the ERP
- Schedule
Programme
Task 2 · 30 min
The full programme: render, painting and the draft's logic
- You produce
- The full programme: all twelve activities with the draft's links
- Document
- AI draft: activities, durations and logic
- In the ERP
- Schedule
Programme
Task 3 · 40 min
Invented links: the logic the AI made up
- You produce
- Links between tasks, without invented ones
- Document
- Design construction sequence
- In the ERP
- Schedule
Programme
Task 4 · 35 min
Critical path and finish: does it fit the period?
- You produce
- Critical path, planned duration, and the margin to the contract term
- Document
- Contract calendar
- In the ERP
- Schedule
Progress and cash
Task 5 · 35 min
Physical progress: measured, not assumed
- You produce
- Planned value, earned value (the value of the work done) and physical progress
- Document
- Inspector's measurement
- In the ERP
- Earned value
Progress and cash
Task 6 · 40 min
S-curve and cash: the physical-financial programme
- You produce
- S-curve and monthly cash
- Document
- Payment terms of the contract
- In the ERP
- Cost and cash
From a draft programme to a cash plan
Each step below is one task. Every later figure depends on the programme being right first.
Blue is what the task adds; grey is carried over from before.
In short. Compute durations from productivity, keep only links with a construction reason, read the longest path, and measure progress rather than assume it.