Theory before task 1 · 8 min

Durations from productivity, not from guesswork

The blockwork duration from the composição

Course introduction

After this lecture you can

  1. Read a unit composition: hours of each trade per unit of work.
  2. Turn quantity, productivity and crew into a duration in working days.
  3. Say why the labourers do not set the duration, and why days round up.
1 / 4

A composition is hours per unit

A unit composition (composição) lists the inputs for one unit of work: materials, and labour as hours of each trade per unit. In SINAPI, the federal cost reference for building work, this coefficient is the unit productivity ratio, RUP: worker-hours divided by quantity of work. Multiply it by the quantity and you have the hours the job needs.

Quantity, m²720
Mason, h per m²0.35
Mason-hours252
2 / 4

The trade that does the work sets the pace

SINAPI's method distinguishes the skilled trades, who produce the finished work, from the labourers in the main compositions, who carry material to them. The duration therefore comes from the skilled trade's hours divided among the skilled workers in the crew. Adding the labourers to the divisor makes the job look faster than it is.

Example. Four masons and two labourers is a crew of four for the duration calculation.
3 / 4

Hours a day come from the calendar

Divide by the hours the site actually works each day: in this case 8 h, Monday to Friday. A fraction of a day still occupies that day, so round up to whole working days.

DurationHours ÷ (skilled workers × hours a day)
ThenRound up to a whole day
4 / 4

What the coefficient leaves out

SINAPI's coefficients do not allow for stoppages caused by rain. Weather risk is handled separately in the programme, as contingency or as a weather calendar, not by quietly changing productivity.

Example. An AI that rounds down, or divides by everyone on site, shortens every finishing activity at once.

Work out a duration

Another job: render to 720 m². Type your answer first.

Not to scale
The problem
  • Composition: mason 0.35 h/m², labourer 0.18 h/m².
  • Crew: 4 masons and 2 labourers. Site works 8 h a day, Monday to Friday.
Quantity720
Mason h/m²0.35
Mason-hours?
Quantity720
Mason h/m²0.35
Mason-hours252
Step 1 of 2

Mason-hours

How many mason-hours does the render need?

720 × 0.35 = 252 hours.

Exact
7.87
Programmed
?
Exact
7.87
Programmed
8 (7.87 + 0.13)
Step 2 of 2

Duration

How many working days does it take?

252 ÷ (4 × 8) = 7.9, rounded up to 8 working days. The labourers keep the masons supplied; they do not add to the masons' output.

In short. Quantity × the skilled trade's coefficient, divided by the skilled workers and the hours a day, rounded up.

Check yourself

Question 1 of 3

Painting 900 m² at 0.19 painter-hours per m², three painters, 8 h a day. How many working days, rounded up?

900 × 0.19 = 171 h; 171 ÷ (3 × 8) = 7.1, so 8 working days.
Question 2 of 3

A crew has three masons and three labourers. How many people divide the mason-hours?

  • Labourers carry material; they do not lay the blocks.

  • The skilled trade sets the pace.

Question 3 of 3

Do SINAPI coefficients allow for rain stoppages?

  • SINAPI states that they do not.

  • As contingency or a weather calendar.