Work out planned value from the programme and earned value from the measurement.
Compute the schedule performance index and the physical progress.
1 / 4
Time elapsed is not work done
A third of the term gone does not mean a third of the work done. Progress is measured on site, activity by activity, by the contract inspector. Law 14.133/2021 ties payment to measurement of the stages of the physical-financial schedule; an estimate from the calendar measures nothing.
Example. A site waiting a month for steel has used time and built nothing with it.
2 / 4
Three values
Budget at completion (BAC) is the value of the whole job. Planned value (PV) at a date is the value the programme said would be done by then. Earned value (EV) is the value of what was measured as done. All three are in contract prices.
BACValue of all activities
PVFrom the programme's dates
EVMeasured % × activity value
3 / 4
Two ratios
The schedule performance index is SPI = EV ÷ PV: below 1, the job is behind its own programme. Physical progress is EV ÷ BAC: the share of the whole job done. They answer different questions; neither uses PV in place of EV.
Planned value
R$420,000
Earned value
R$420,000 (R$357,000 + R$63,000)
4 / 4
PV follows the corrected programme
Planned value comes from each activity's planned dates in the corrected programme, not from the contract value spread evenly over the term. If external works were planned to start early, part of their value is planned by the measurement date.
Example. An activity planned half done by the date contributes half its value to PV.
Measure a month
Another job. BAC R$800,000. Type your answer first.
Not to scale
The problem
Planned value at the measurement date, from the corrected programme: R$370,000.
Measured: site set-up R$96,000 at 100 %, foundations R$150,000 at 100 %, frame R$100,000 at 50 %. Nothing else started.
R$96,000R$150,000R$50,000
Set-up R$96,000
Foundations R$150,000
Half the frame R$50,000
R$96,000R$150,000R$50,000
Set-up R$96,000
Foundations R$150,000
Half the frame R$50,000
Step 1 of 3
Earned value
What is the earned value?
Hint: Measured percentage times each activity's value.