Theory before task 5 · 8 min

Progress: measured, not assumed

Physical progress: measured, not assumed

After this lecture you can

  1. Tell elapsed time from physical progress.
  2. Work out planned value from the programme and earned value from the measurement.
  3. Compute the schedule performance index and the physical progress.
1 / 4

Time elapsed is not work done

A third of the term gone does not mean a third of the work done. Progress is measured on site, activity by activity, by the contract inspector. Law 14.133/2021 ties payment to measurement of the stages of the physical-financial schedule; an estimate from the calendar measures nothing.

Example. A site waiting a month for steel has used time and built nothing with it.
2 / 4

Three values

Budget at completion (BAC) is the value of the whole job. Planned value (PV) at a date is the value the programme said would be done by then. Earned value (EV) is the value of what was measured as done. All three are in contract prices.

BACValue of all activities
PVFrom the programme's dates
EVMeasured % × activity value
3 / 4

Two ratios

The schedule performance index is SPI = EV ÷ PV: below 1, the job is behind its own programme. Physical progress is EV ÷ BAC: the share of the whole job done. They answer different questions; neither uses PV in place of EV.

Planned value
R$420,000
Earned value
R$420,000 (R$357,000 + R$63,000)
4 / 4

PV follows the corrected programme

Planned value comes from each activity's planned dates in the corrected programme, not from the contract value spread evenly over the term. If external works were planned to start early, part of their value is planned by the measurement date.

Example. An activity planned half done by the date contributes half its value to PV.

Measure a month

Another job. BAC R$800,000. Type your answer first.

Not to scale
The problem
  • Planned value at the measurement date, from the corrected programme: R$370,000.
  • Measured: site set-up R$96,000 at 100 %, foundations R$150,000 at 100 %, frame R$100,000 at 50 %. Nothing else started.
R$96,000R$150,000R$50,000
  • Set-up R$96,000
  • Foundations R$150,000
  • Half the frame R$50,000
R$96,000R$150,000R$50,000
  • Set-up R$96,000
  • Foundations R$150,000
  • Half the frame R$50,000
Step 1 of 3

Earned value

What is the earned value?

R$96,000 + R$150,000 + 50 % × R$100,000 = R$296,000.00.

PV
R$370,000
EV
R$296,000
PV
R$370,000
EV
R$296,000
Step 2 of 3

SPI

What is the SPI, to two decimals?

R$296,000.00 ÷ R$370,000 = 0.8: the job is behind its programme.

BAC
R$800,000
EV
R$296,000
BAC
R$800,000
EV
R$296,000
Step 3 of 3

Physical progress

What is the physical progress, in per cent?

R$296,000.00 ÷ R$800,000 = 37%.

In short. PV from the programme, EV from the measurement, SPI = EV ÷ PV, physical progress = EV ÷ BAC.

Check yourself

Question 1 of 2

A draft reports progress as days elapsed over days of the term. What is wrong?

  • Time passing builds nothing.

  • EV ÷ BAC, from what the inspector measured.

Question 2 of 2

EV R$216,000, PV R$240,000. What is the SPI?

216 ÷ 240 = 0.9.