Read the critical path and the planned duration in working days.
Count a contract term in calendar days the way Law 14.133/2021 counts.
Compare dates, not numbers of days from two different calendars.
1 / 4
The critical path is the longest
With the logic corrected, the critical path is the chain of activities with zero float. Its length in working days is the planned duration. Every other path is shorter and has float. When two paths are close, both deserve watching.
Example. A path that is one day shorter than the critical one is nearly critical: one bad day makes it critical.
2 / 4
The contract counts calendar days
Law 14.133/2021 (article 183) counts its periods by excluding the day of the start and including the last day, in continuous calendar days. The case contract applies the same rule to the period of performance. So the term ends exactly that many calendar days after the order to start.
Order to startDay 0, excluded
Term of 60 daysEnds on day 60, included
Weekends and holidaysCounted
3 / 4
Two calendars, so compare dates
The programme counts working days; the contract counts calendar days. A programme of 36 working days is not 36 days of a 60-day term. Turn both into dates, the planned finish and the contractual term, and the margin is the calendar days between them.
Example. Comparing 36 with 60 directly overstates the margin by every weekend in between.
Programme, working days
36
Term, calendar days
60
4 / 4
Holidays are part of the calendar
National holidays are set by federal law and fall on working days in some years; states and municipalities add their own. A working-day programme must leave them out; a calendar-day term ignores them. Check both before you publish a finish date.
Example. A programme that runs through 7 September has to know whether that day is a working day that year.
Will it fit?
Another job. Order to start on Monday 5 July 2027; work starts that day. Monday to Friday; no holiday falls on a working day in the period. Term: 60 calendar days.
Not to scale
The problem
Two paths through the corrected programme: 36 and 26 working days.
The planned finish is the 36th working day counting from 5 July: Monday 23 August 2027.
The term: 5 July plus 60 calendar days, start day excluded.
Path 1
36
Path 2
36 (26 + 10)
Path 1
36
Path 2
36 (26 + 10)
Step 1 of 2
Planned duration
What is the planned duration, in working days?
Hint: The longest path.
36 working days. The shorter path has 36 − 26 days of float.
Planned finish23 August 2027
End of term3 September 2027
Margin, calendar days?
Planned finish23 August 2027
End of term3 September 2027
Margin, calendar days11
Step 2 of 2
Margin
How many calendar days are there between the planned finish and the end of the term?
Hint: The term ends on 3 September 2027.
From 23 August to 3 September: 11 calendar days. It fits, with a margin of under two weeks.
In short. Read the longest path in working days, turn it into a date, count the term in calendar days without the start day, and compare the two dates.
Check yourself
Question 1 of 2
An order to start is dated 1 March; the term is 90 days. Which day is day 1 of the count?
The start day is excluded.
Excluding the start, including the end.
Question 2 of 2
A programme of 36 working days and a term of 60 calendar days. What is the margin?