Theory before task 5 · 9 min

Sign the sum you can defend

The row that was never produced, and the sum you sign

After this lecture you can

  1. Add a missing markup row in the right place and say why the order of rows changes the result.
  2. Test a tender sum against a rate per m² before you sign.
  3. Say what a benchmark test proves, and what it does not.
1 / 3

A row that was never produced

Assistants build what they were asked for and often forget rows that were implied, such as insurance and bonds. When the row is missing, the bid is cheaper than the firm intended and nobody notices, because every total still adds up. Check the stack against the written rules of the firm, row by row, rather than against the last figure you saw.

Example. A tender that adds up can still be wrong; it adds up with a row missing.
2 / 3

Where the row goes matters

A row above profit changes the base that profit stands on, so it moves profit too. The same row below profit would not. Put each row where the rule says; the order is part of the rule. When you add a row, re-read every row below it: its amount changes even though you did not touch it.

Example. The row's own amount is not the full effect. Profit at 5 % on top of it adds a little more.
Insurance row added above profit€24,600
Effect on the tender, profit included€25,830
3 / 3

The per m² test

Divide the tender sum by a physical measure, here the floor area, and compare with a range from similar jobs. The test finds large errors: a missing zero, a section left out. It cannot find a small one, and it cannot find errors that offset each other. A figure inside the range is not evidence that the bill is right; it is only evidence that it is not absurd. Sign the sum for what you checked, and say what you did not.

Example. The report to your manager lists: what was verified, what was corrected, and what the test cannot show.

Add the row and read the sum

Different numbers from your task.

Not to scale
The problem
  • Direct cost €1,640,000. Tender without the insurance row: €2,000,000. Insurance and bonds 1.5% on direct cost, placed above profit. Profit 5% on the running total. Floor area 4,800.00 m².
Step 1 of 3

The row

Percentage of direct cost. What is the insurance amount?

1.5% of €1,640,000 = €24,600.

Step 2 of 3

The change in the tender

The row sits above profit, so profit grows by its own percentage of it. What is the effect on the tender?

€24,600 plus 5% on it = €25,830.

Step 3 of 3

The tender per m²

New tender divided by floor area. What is the figure?

(€2,000,000 + €25,830) ÷ 4,800.00 m² = €422.05 per m².

In short. Add the row where the rule puts it, read the knock-on effect on the rows below, and sign only what you tested.

Check yourself

Question 1 of 3

A row is added below profit instead of above. What changes?

  • Profit is taken on the rows above it, so moving a row changes profit.

  • The row is outside profit's base, so no profit is added to it.

  • Nothing doubles; the amount is the same but the profit on it is gone.

  • It accepts it and the difference is small enough to pass unnoticed.

Question 2 of 3

The tender per m² falls inside the firm's usual range. What does that show?

  • It shows only that the total is plausible. Offsetting errors and small ones pass.

  • That is what a range test is good for.

  • The test has no access to rate sources.

  • Order changes the total by a fraction of a percent; the test cannot see it.

Question 3 of 3

Direct cost 900,000. An insurance row of 1.5 % on direct cost goes above profit; profit is 5 % on the running total. By how much does the tender rise?

Row 13,500; with profit 13,500 × 1.05 = 14,175.