OpenConstruction Academy
Sign in / Register
EN

Theory before task 4 · 10 min

Which base does each markup stand on

The markup stack: the right percentage on the wrong base

After this lecture you can

  1. Name the base of preliminaries, overheads, insurance and profit and say why they differ.
  2. Calculate a stack from the bottom row to the tender sum.
  3. Spot the right percentage on the wrong base.
1 / 3

The stack is a recipe, not a list of percentages

Below the bill sits the markup stack: rows added in order until the tender sum is reached. Each row has two properties: a percentage or a fixed amount, and a base, the figure that percentage is taken from. Two stacks with identical percentages give different totals if the bases differ. That is why the base is as important as the rate, and why an assistant that remembers 'overheads 7 %' can still get the tender wrong.

Example. Always read a row as 'percentage of what?'
2 / 3

Three kinds of base

Fixed amount: preliminaries are priced from a schedule of site costs (cabins, crane, management) and enter as a sum, not as a percentage. Direct cost: overheads and insurance are percentages of the cost of the work itself. Cumulative: profit is a percentage of everything above it, direct cost plus the rows already added. A common mistake is to take profit on direct cost only, which understates it, or to take overheads on a base that already includes preliminaries, which overstates it.

Example. Illustrative figures. Profit stands on the running total, so it also earns profit on the preliminaries and overheads.
€860,0001+€70,5002+€60,2003+€39,6284€1,030,3285
  • 1 Direct cost
  • 2 Preliminaries (fixed)
  • 3 Overheads (on direct cost)
  • 4 Profit (on running total)
  • 5 Tender
3 / 3

Read the stack both ways

From the top: take the tender sum, divide out the rows, and you should land on the direct cost. From the bottom: add row by row. When the two directions disagree, a base is wrong. Also check that the software's setting matches the written rule. The words differ by package, but the three bases are the same: fixed, on direct cost, and on the running total. A row set to 'sum of positions' is on direct cost; a row set to a running total includes the rows above it.

Example. Rounding is done once, at the end, with full precision carried through the rows. A rounded row in the middle moves the tender by a few cents; it is a symptom, not a cause.

Build a stack and test a wrong base

Different numbers from your task.

Not to scale
The problem
  • Direct cost €860,000. Preliminaries from the schedule: €70,500. Overheads 7% on direct cost. Profit 4% on direct cost plus the rows above.
Step 1 of 3

Overheads

Percentage of the direct cost only. What is the amount?

7% of €860,000 = €60,200.

Step 2 of 3

Profit

Percentage of direct cost plus preliminaries plus overheads. What is the profit?

(€860,000 + €70,500 + €60,200) × 4% = €39,628.

Step 3 of 3

Understatement from the wrong base

If profit were taken on direct cost only, how much would the tender be short?

Right profit €39,628 minus 4% of €860,000 = €5,228.

In short. Each row has a base. Fixed, on direct cost, on the running total: read every row as a percentage of what.

Check yourself

Question 1 of 3

Overheads are set up as a percentage of a base that already includes preliminaries. What happens?

  • The base is too big, so the same percentage gives too much.

  • Preliminaries are priced separately and have their own base. Overheads are defined on direct cost.

  • Profit is a separate row on its own base; overstated overheads would, if anything, raise it.

  • It accepts any base. The error stays silent unless you read each row.

Question 2 of 3

What is the base of the profit row in this stack?

  • That ignores the rows above it and understates profit.

  • Correct: profit is taken on everything the tender already contains.

  • Profit cannot be taken on a total that contains it.

  • They are one input, not the base.

Question 3 of 3

Direct cost 500,000. Preliminaries 40,000. Overheads 6 % on direct cost. Profit 5 % on the running total. What is the profit?

Running total = 500,000 + 40,000 + 30,000 = 570,000; × 5 % = 28,500.