Theory before task 3 · 10 min

Build a net rate from resources

Build-ups: the assistant's own estimate, and what it quietly includes

After this lecture you can

  1. Build a unit rate from material, waste and lap, labour and plant, and keep it net.
  2. Explain why a markup already inside a rate is counted twice when the stack adds it again.
  3. Say what to do when the library has no row for an item.
1 / 3

When there is no row

A library cannot hold every item. When it has none, you do not accept the assistant's guess; you build the rate from resource rates. The build-up is a short sum that anyone can read: materials with their allowances, labour as hours times an hourly cost, and plant as a rate for the time it is on the job. A build-up is allowed because each line in it has a source of its own.

Example. Write every ingredient on its own line with its unit, so the next person can change one number without rebuilding the rest.
2 / 3

What goes in, and the allowances

Materials are bought in whole sheets, rolls and lorry loads, so quantities carry waste (the offcuts and spillage you cannot avoid) and laps (the overlap of fabric or membrane, which covers area twice). Express both as a percentage on the material, as an estimator does: the rate is for one square metre in place, not one square metre bought. Labour is the hours one gang needs for one unit, times the cost of an hour. Plant is the machine cost divided over the unit. Nothing else goes in a net rate.

Example. Each part is real cost. There is no row for 'something for the office' or 'a margin'.
€21.20€10.90
  • Concrete with waste €21.20
  • Fabric with laps €4.70
  • Labour €10.90
  • Plant €1.60
3 / 3

The markup that hides in a rate

Preliminaries, overheads, insurance and profit are paid once, in the markup stack under the bill. If an assistant adds a flat percentage to its own estimate, 'to cover overheads and profit', that percentage is now inside the rate and the stack adds it again. The tender pays for the same overhead twice, and the bid is dearer than it needs to be. The test is simple: ask what each ingredient of the rate is. If one is a percentage that is not waste or lap, it is a markup and it comes out.

Example. The loaded rate looks reasonable beside the net one. On a large quantity the gap is a real sum of money.
Net build-up
€38.30
Same rate with 25 % loaded in
€47.90

Build a slab rate and see the load

Different numbers from your task.

Not to scale
The problem
  • Yard slab, per m²: concrete 0.18 m thick at €112.00 per m³ with 5% waste; fabric €4.10 per m² with 15% lap; labour 0.35 hours at €31.00; plant €1.60.
  • The assistant loaded 20% for overheads and profit into its rate. Slab area 1,800.00 m².
Step 1 of 3

Net rate

Concrete with waste, fabric with lap, labour and plant. What is the net rate per m²?

Concrete 0.18 m × €112.00 plus waste; fabric €4.10 plus lap; labour 0.35 × €31.00; plant €1.60. Net rate €38.33.

Step 2 of 3

The rate the assistant would use

Add the loaded percentage to the whole net rate. What is its rate?

€38.33 plus 20% = €46.00.

Step 3 of 3

What the load costs

On the full area, by how much is the loaded line above the net line?

1,800.00 m² × (€46.00 − €38.33) = €13,800. The stack would add the real overhead on top of this.

In short. Build from resources, keep it net, and let the markup stack carry overheads and profit once.

Check yourself

Question 1 of 3

The assistant adds a flat percentage to its own estimate of an item 'to cover overheads and profit'. What is wrong?

  • Commonness is not the issue. The stack adds overheads and profit again, so the bid pays twice.

  • Net rates carry cost. Overheads and profit belong in the markup stack, once.

  • A higher figure would make the double count larger.

  • Quantity is measured, not marked up.

Question 2 of 3

Fabric is laid with a 15 % lap. What does the lap do to the rate?

  • It is real material you buy and place; the rate must carry it.

  • Laps are overlaps, so you buy more than the area covered.

  • Labour is time; a lap is extra material.

  • A markup is for risk, overhead or profit. A lap is real cost of the item.

Question 3 of 3

A net rate is 52.00 per m². The assistant's rate carries 25 % on it. What does it overstate the line by on 800 m²?

25 % of 52.00 = 13.00 per m²; 800 × 13.00 = 10,400.