OpenConstruction Academy
Sign in / Register
EN

Course introduction · 3 min

Client-side risk and funding approval (UK, NEC4)

You are the Project Manager for the Client on a two-storey health centre in England, appointed under NEC4. Before the contract is signed the Partnership's board must fund it, and nobody has priced the risk the contract leaves with the Client. In five tasks you build that figure, take it to the board and keep it honest when the job starts.

Start task 1

The health centre site in England, a fictional project.Fictional project
Ashbrook Community Health CentreFunding board, December 2026 · month 2 review, February 2027
Contract
NEC4 Engineering and Construction Contract, Option B; Prices 1,169,739.13
Client
A district health partnership whose board signs the funding
Register
Risk Register in the ERP: the Client's risks, their EMV and P80
Work in the ERP
5 tasks, about 1 h 30 min

Who hands what to whom

Every arrow is a figure or a decision that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Funding workshopNames the risks
    • Six risks, one not yoursTask 1
  • ContractorBuilds under NEC4
    • Notice of the old footingTask 4
YouProject Manager for the Client

Goes from you

    • Envelope and reserveTask 2
    • Cost of late openingTask 3
    • Funding after month 2Task 4
    The Partnership's boardSigns the funding
    • Yes or noTask 5
    Equipment plannerOffers a layout freeze

The project and the people are fictional. Portraits are generated.

Your route through the job

Three tasks build the board's figure, two keep it true once work starts. Start with task 1: in Risk Register you record the Client's risks and read their expected cost.

  1. Fund

    Task 1 · 12 min

    Whose risk is it?

    You produce
    The Client's register and its EMV
    Document
    Funding workshop notes
    In the ERP
    Risk Register
  2. Fund

    Task 2 · 18 min

    P80: the figure the board funds

    You produce
    One more risk, the funding envelope at P80 and the board's reserve
    Document
    Funding policy
    In the ERP
    Risk Register
  3. Fund

    Task 3 · 20 min

    What a late opening costs the Partnership

    You produce
    The expected cost of a late opening
    Document
    Lease and temporary rooms
    In the ERP
    Risk Register
  4. Manage

    Task 4 · 20 min

    Month 2: a risk happened, one went away

    You produce
    The register at month 2 and the funding it needs
    Document
    Review notes
    In the ERP
    Risk Register
  5. Manage

    Task 5 · 20 min

    Is the layout freeze worth paying for?

    You produce
    A treatment bought or turned down, on the money
    Document
    The planner's offer
    In the ERP
    Risk Register

From a list of worries to a figure a board can sign

Each step below is one task.

EMV
Task 1OwnOnly what the contract leaves with the Client, at its expected cost.
ReserveEMV
Task 2FundP80, split between the Project Manager and the board.
DelayRisk
Task 3TimeThe Client's own cost of opening late.
Now
Task 4ReviewWhat happened counts in full; what went away counts nothing.
PriceAfter
Task 5TreatPay to reduce a risk when it saves more than it costs.

Blue is what the task adds; grey is carried over from before.

In short. Fund only the Client's risks, at a confidence the board chooses, and keep the figure true as the job runs.