Theory before task 1 · 7 min

Whose risk is it? The Client's register under NEC4

Whose risk is it?

Course introduction

After this lecture you can

  1. Tell a Client's risk from a Contractor's by the contract, not by size.
  2. Work out the expected monetary value of a register.
  3. Keep the Contractor's risks out of the Client's funding.
1 / 3

The contract has already decided

Under NEC4 a risk is the Client's when it is one of the compensation events in clause 60.1: the Project Manager changes the Scope, the Client is late with something it must provide, Others such as a utility work late, the ground holds what an experienced contractor could not have allowed for, or the weather is worse than the ten-year record. Everything else is priced in the Contractor's Prices. The Client's register lists the first group, and only that group.

Example. A utility diverting a main late is Others working late: the Client's. The Contractor's own masonry gang working slowly is not.
2 / 3

Expected monetary value

For each risk, the expected monetary value (EMV) is its probability times what it costs if it happens. Added over the register, it is the cost the Client should expect to pay for risk across the job. No single risk ever costs its EMV: it costs nothing or its full amount.

Example. A register of three Client's risks on another job: the bar is their EMV, £8,250.
£4,500£1,500£2,250
  • Late utility, 0.25 × £18,000 £4,500
  • Design change, 0.50 × £3,000 £1,500
  • Weather, 0.30 × £7,500 £2,250
Common mistake

Funding the Contractor's risks too

A workshop names every worry in the room, the Contractor's included. A material price rise under Option B without the X1 inflation option is already in the Contractor's Prices. Putting it on the Client's register funds it twice and teaches the board that risk money is spare money.

Example. Ask of each row: if this happens, who pays under the contract? If the answer is the Contractor, it stays off.

A register for the car park works

A different package on another job, with its own figures.

Not to scale
The problem
  • Late utility (Others): 0.25 × £18,000.
  • Design change by the Client: 0.5 × £3,000.
  • Weather beyond the ten-year return: 0.3 × £7,500.
Step 1 of 3

Largest risk

EMV of the late utility?

0.25 × £18,000 = £4,500.00.

Step 2 of 3

The register

EMV of all three?

£4,500.00 + 1,500 + 2,250 = £8,250.00.

Step 3 of 3

Worst case

Cost if all three happen?

£18,000 + £3,000 + £7,500 = £28,500.00.

In short. EMV is the expected cost of the register; the worst case is every risk at once.

Check yourself

Question 1 of 2

Under NEC4 Option B without X1, who carries a steel price rise?

  • Only with X1 does the Client share price changes.

  • Right.

  • NEC has no such default.

Question 2 of 2

Two Client's risks: 0.4 × £5,500 and 0.1 × £35,000. What is the EMV?

2,200 + 3,500 = £5,700.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.