The contract has already decided
Under NEC4 a risk is the Client's when it is one of the compensation events in clause 60.1: the Project Manager changes the Scope, the Client is late with something it must provide, Others such as a utility work late, the ground holds what an experienced contractor could not have allowed for, or the weather is worse than the ten-year record. Everything else is priced in the Contractor's Prices. The Client's register lists the first group, and only that group.