Client-side risk and funding approval (UK, NEC4)

Work as the Client's Project Manager on a new health centre: register the risks NEC4 leaves with the Client, fund them at P80 with a board reserve, price what a late opening costs the Partnership, update the funding when a risk happens and decide whether a treatment pays.

Workspace: Client-side risk and funding approval (UK, NEC4)
Whose risk is it?

Who this course is for

Project Manager for the Client (NEC4 ECC Option B) — The project and people are invented for training. The rules and contract forms are real.
Your role in the caseProject Manager for the Client (NEC4 ECC Option B)
Cost consultancy — The project and people are invented for training. The rules and contract forms are real.
The company in the caseCost consultancy

The project and people are invented for training. The rules and contract forms are real.

You will be able to

Skills checked

  • Register the risks NEC4 leaves with the Client and give their expected cost (EMV)
  • Fund the Client's risk at P80 and split it into the Project Manager's EMV and the board's reserve
  • Price the expected cost of a late opening from the delay days on the risk register
  • Update the register when a risk occurs or closes and state the funding the board must add
  • Decide whether a risk treatment pays, counting construction cost and the cost of opening late

Tasks

A task as it opens in the trainer, before you enter anything.

Task 1 as it opens in the trainer: Whose risk is it?
  1. 1
    Whose risk is it?FreeFoundation≈12 minTheory · 7 min
  2. 2
    P80: the figure the board fundsPaidFoundation≈18 minTheory · 8 min
  3. 3
    What a late opening costs the PartnershipPaidFoundation≈20 minTheory · 7 min
  4. 4
    Month 2: a risk happened, one went awayPaidFoundation≈20 minTheory · 6 min
  5. 5
    Is the layout freeze worth paying for?PaidFoundation≈20 minTheory · 7 minCheat sheet: every rule on one page

Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks. The free tasks give a progress badge, not the certificate.

The certificate is included in the price.

Certificates

Sample: Professional certificate
Sample issued to a fictitious learner. Your certificate shows your name, the course, the date and its own ID.
Check this sample

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • parties4 records

Prices

€39one paymentPrice when sales open

Task 1 is free. Pay only if you want to go on. Start task 1 free

  • All 5 tasks and the professional certificate
  • No subscription, nothing renews
  • No VAT added: the price is the total

Cheaper in the bundle United Kingdom: 6 courses for €229 instead of €334

Buy now · €39

Course not as described? We fix it or refund you.

Need a discount? Write to info@datadrivenconstruction.io

How pricing works

What next

Next in the learning pathDeveloper cost check: can we pay the asking price? (UAE)Advanced · 1.5 h of study

When you pass, add the certificate to LinkedIn from your account. Anyone can open its verification link, no sign-in needed. How to add it

Questions about this course? Write to info@datadrivenconstruction.io