OpenConstruction Academy
Sign in / Register
EN

Theory before task 3 · 7 min

Time is the Client's cost too

What a late opening costs the Partnership

After this lecture you can

  1. Explain why a compensation event's delay costs the Client twice.
  2. Work out the expected delay of a register.
  3. Price it per working day.
1 / 3

What a Client's risk does to the opening date

When a compensation event delays planned Completion, the Completion Date moves with it. The Contractor is paid its cost and given the time; no delay damages run. The Client still waits for its building, and pays its own costs of waiting: the old premises, temporary rooms, staff who cannot move in. None of that is in the Contractor's quotation.

Example. A clinic that opens three weeks late pays three more weeks of rent on the building it was leaving.
2 / 3

Expected delay

Weight each risk's delay by its probability and add them up, as for EMV. Price it at the Client's cost per working day: the weekly cost divided by five.

Example. Three risks on another job: 4.1 working days expected.
0.20 × 10 working days2
0.50 × 3 working days1.5
0.30 × 2 working days0.6
Expected delay, working days4.1
Common mistake

Adding the days in full

Adding every risk's days in full gives the delay if everything goes wrong at once, which the board will not believe and should not fund. Weight the days, as you weighted the cost.

Example. Ten, three and two days are fifteen in full, but only 4.1 expected.

Pricing a late opening

The three risks above, with the client's own costs.

Not to scale
The problem
  • Expected delay 4.1 working days.
  • The client's cost of waiting: £3,000 a week.
Step 1 of 2

Per day

Cost per working day?

£3,000 ÷ 5 = £600.00.

Step 2 of 2

Expected cost

Expected cost of late opening?

4.1 × £600.00 = £2,460.00.

In short. Expected days × the client's cost per working day.

Check yourself

Question 1 of 2

A compensation event delays Completion by two weeks. Who pays the Client's temporary rooms?

  • The Completion Date moved, so no damages run.

  • Right.

  • This is not an insured loss.

Question 2 of 2

Expected delay 6 working days; the client pays £2,750 a week. Expected cost?

6 × 550 = £3,300.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.