What a Client's risk does to the opening date
When a compensation event delays planned Completion, the Completion Date moves with it. The Contractor is paid its cost and given the time; no delay damages run. The Client still waits for its building, and pays its own costs of waiting: the old premises, temporary rooms, staff who cannot move in. None of that is in the Contractor's quotation.