A register has outcomes, not one cost
Each risk happens or not. Two risks give four outcomes: neither, one, the other, both. Each outcome has a cost and a chance. Sort the outcomes by cost and add up the chances: the cost where the running total first reaches 80 % is P80. The money is enough in four outcomes of five.