OpenConstruction Academy
Sign in / Register
EN

Theory before task 2 · 8 min

P80: funding at a confidence, not at the average

P80: the figure the board funds

After this lecture you can

  1. Read P80 off the outcomes of a register.
  2. Split the funding into what the Project Manager holds and what the board keeps.
  3. Avoid counting an early optimism-bias uplift on top of a costed register.
1 / 3

A register has outcomes, not one cost

Each risk happens or not. Two risks give four outcomes: neither, one, the other, both. Each outcome has a cost and a chance. Sort the outcomes by cost and add up the chances: the cost where the running total first reaches 80 % is P80. The money is enough in four outcomes of five.

Example. Risk A 0.30 × £10,000 and risk B 0.50 × £4,500: the running total passes 80 % at £10,000, so P80 is £10,000 while the EMV is £5,250.
Neither, 35 %
£0
Only B, 35 % (70 % so far)
£4,500
Only A, 15 % (85 % so far)
£10,000
Both, 15 %
£14,500
2 / 3

Who holds what

Many public clients split risk money. The project team manages up to the expected cost; the sponsor or board keeps the rest up to the chosen confidence and releases it only by decision. Money that sits in one pot gets spent by default.

Example. In the example the Project Manager holds £5,250 and the board £4,750 more, up to P80.
Common mistake

Optimism bias on top of a costed register

At an early business case the Green Book adds an optimism-bias uplift for risks nobody has costed yet. Once the risks are on a register with probabilities and costs, the uplift comes down. Carrying both counts the same risk twice.

Example. Funding = Prices + P80 of the register, not Prices + P80 + the early uplift.

Two risks, step by step

The two-risk example from the explainer.

Not to scale
The problem
  • Risk A: 0.3 × £10,000. Risk B: 0.5 × £4,500.
  • Prices £250,000. The board funds Prices plus P80.
Step 1 of 4

EMV

EMV of the two risks?

3,000 + 2,250 = £5,250.00.

Step 2 of 4

P80

Cost at P80?

The running total first reaches 80 % at £10,000.00.

Step 3 of 4

Envelope

Funding envelope?

£250,000 + £10,000.00 = £260,000.00.

Step 4 of 4

Reserve

What the board keeps?

£10,000.00 − £5,250.00 = £4,750.00.

In short. P80 comes from the sorted outcomes; the board keeps P80 less the EMV.

Check yourself

Question 1 of 2

At the EMV, how often does the money run out?

  • The EMV is an average; many outcomes cost more.

  • Right.

  • That is P80.

Question 2 of 2

P80 is £40,000 and the EMV £27,500. What does the board keep?

40,000 − 27,500 = £12,500.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.