Theory before task 4 · 6 min

Reviewing the register: occurred and closed

Month 2: a risk happened, one went away

After this lecture you can

  1. Set a risk to Occurred or Closed for the right reason.
  2. See why a risk that happens raises the money needed.
  3. Report the change against what the board funded.
1 / 3

Three states, three weights

An open risk counts at its probability. A risk that has happened counts in full: its cost is no longer a chance. A risk that can no longer happen is closed and counts nothing. Closed risks stay on the register as the record of how the job was managed.

Example. A weather risk for the frame closes once the frame is up; a ground risk occurs when the old footing is found.
Open: cost × probabilityopen
Occurred: cost × 1in full
Closed: cost × 0nothing
2 / 3

Why funding can rise after a risk happens

The funding held each risk at its chance. When one happens, its whole cost is now certain, so the money needed rises by the part that was never held. Only risks that close give money back. The review weighs the two and compares the new P80 with the P80 the board funded.

Example. A 0.25 × £12,000 risk held £3,000 of expected cost; when it happens it needs £12,000.
Common mistake

Closing what happened

A risk that happened is not over: its cost is still to be paid. Set it to Occurred until the money is spent; Closed would make the funding look better on the day the Client learnt it is worse.

Example. Occurred until the compensation event is implemented and paid; then it can be closed.

A review on another job

Two risks: one happens, one closes.

Not to scale
The problem
  • Risk A 0.25 × £12,000 happens. Risk B 0.5 × £7,400 closes.
Step 1 of 2

Before

Expected cost before?

3,000 + 3,700 = £6,700.00.

Step 2 of 2

After

Expected cost after?

£12,000 + 0 = £12,000.00.

In short. Occurred in full, closed at nothing: the expected cost rose although one risk went away.

Check yourself

Question 1 of 2

The old footing has been found but not yet priced. Status?

  • Its cost is still to come.

  • Right.

  • It is no longer a chance.

Question 2 of 2

An open risk 0.2 × £15,000 occurs. By how much does the expected cost rise?

15,000 − 3,000 = £12,000.