Theory before task 5 · 7 min

Paying to reduce a Client's risk

Is the layout freeze worth paying for?

After this lecture you can

  1. Value a treatment by the drop in probability it buys.
  2. Include the Client's cost of delay in the saving.
  3. Keep the residual risk on the register.
1 / 3

What a treatment buys

A treatment changes the chance or the size of a risk. Its value is the expected cost it removes: the drop in probability times what the risk costs if it happens. Pay for it when that is more than its price.

Example. On another job a design review cuts a 0.5 × £14,000 risk to 0.1: it saves £5,600 for a £4,200 fee.
Expected saving
£5,600
Price of the treatment
£4,200
2 / 3

For a Client, time is part of the cost

When a Client's risk happens, the Client pays the compensation event and its own cost of the delay. A treatment that lowers the chance saves both, so value it on both.

Example. Cost if it happens = the event's cost + its days × the client's cost per working day.
Common mistake

Leaving the delay out

Valued on construction cost alone, many Client treatments look poor value and are turned down. The opening date is often where most of the saving is.

Example. Add the days before you decide, then decide on the money.

A design review on another job

One Client's risk and an offer to reduce it.

Not to scale
The problem
  • Risk: £14,000 and 4 working days if it happens; the client's delay cost £600 a working day.
  • Review fee £6,300; probability from 0.5 to 0.1.
Step 1 of 3

Cost if it happens

Construction plus delay?

£14,000 + 4 × £600 = £16,400.00.

Step 2 of 3

Saving

Expected saving?

0.4 × £16,400.00 = £6,560.00.

Step 3 of 3

Net

Net benefit?

£6,560.00 − £6,300 = £260.00.

In short. Without the delay the review saves £5,600 and fails; with it, it pays.

Check yourself

Question 1 of 2

After the treatment, the risk is…

  • It can still happen.

  • Right.

  • The owner does not change.

Question 2 of 2

Probability 0.4 to 0.1; cost if it happens £23,000; treatment £5,200. Net benefit?

6,900 − 5,200 = £1,700.