Client-side risk and funding approval (UK, NEC4)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The contract decides whose risk it is. The Client funds only the events NEC4 leaves with it.
- How it is built
- Client's risk EMV = R-001 p × cost + R-002 p × cost + R-003 p × cost + R-004 p × cost + R-005 p × cost
- Usual mistake
- Your figure includes row 6. A price rise under Option B without X1 is the Contractor's: leave it out, and delete R-006 or set it to Closed if you created it.
- At work
- The Client's Project Manager keeps this register for the sponsor; it is separate from the contract's Early Warning Register.
- Rule
- Fund at a confidence, not at the average. The Project Manager holds the EMV; the board keeps the rest up to P80.
- How it is built
- Funding envelope = Prices + P80
- Board reserve = P80 − EMV
- Usual mistake
- You funded the EMV. The policy funds P80.
- At work
- Public clients commonly fund a confidence level and hold the slice above the expected cost centrally.
- Rule
- A Client's risk costs the Client twice. The compensation event, and the wait for the building.
- How it is built
- Expected delay = Σ probability × Days
- Cost of late opening = Expected delay × 4,250.00 ÷ 5
- Usual mistake
- The days were not weighted by probability.
- At work
- Sponsors carry the cost of late opening (decant, double running) in their own budget, beside the construction risk.
- Rule
- What happened counts in full; only what went away gives money back.
- How it is built
- Further funding = New P80 − P80 funded in task 2
- Usual mistake
- R-001 is closed. It happened and its cost is still to come: Occurred, not Closed.
- At work
- The Project Manager reviews the Client's register with each cost report and reports against the funded P80.
- Rule
- For a Client, the saving includes the opening date. Value a treatment on cost and delay together.
- How it is built
- Net benefit = Drop in probability × (cost + delay) − Offer
- Usual mistake
- Only the construction cost counted. A layout change also delays opening; add the delay cost.
- At work
- Clients buy treatments (surveys, design freezes, early utility orders) when they save more than they cost, delay included.