Cheat sheet

Client-side risk and funding approval (UK, NEC4)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Whose risk is it?

Theory (7 min)
Rule
The contract decides whose risk it is. The Client funds only the events NEC4 leaves with it.
How it is built
  • Client's risk EMV = R-001 p × cost + R-002 p × cost + R-003 p × cost + R-004 p × cost + R-005 p × cost
Usual mistake
Your figure includes row 6. A price rise under Option B without X1 is the Contractor's: leave it out, and delete R-006 or set it to Closed if you created it.
At work
The Client's Project Manager keeps this register for the sponsor; it is separate from the contract's Early Warning Register.

Task 2

P80: the figure the board funds

Theory (8 min)
Rule
Fund at a confidence, not at the average. The Project Manager holds the EMV; the board keeps the rest up to P80.
How it is built
  • Funding envelope = Prices + P80
  • Board reserve = P80 − EMV
Usual mistake
You funded the EMV. The policy funds P80.
At work
Public clients commonly fund a confidence level and hold the slice above the expected cost centrally.

Task 3

What a late opening costs the Partnership

Theory (7 min)
Rule
A Client's risk costs the Client twice. The compensation event, and the wait for the building.
How it is built
  • Expected delay = Σ probability × Days
  • Cost of late opening = Expected delay × 4,250.00 ÷ 5
Usual mistake
The days were not weighted by probability.
At work
Sponsors carry the cost of late opening (decant, double running) in their own budget, beside the construction risk.

Task 4

Month 2: a risk happened, one went away

Theory (6 min)
Rule
What happened counts in full; only what went away gives money back.
How it is built
  • Further funding = New P80 − P80 funded in task 2
Usual mistake
R-001 is closed. It happened and its cost is still to come: Occurred, not Closed.
At work
The Project Manager reviews the Client's register with each cost report and reports against the funded P80.

Task 5

Is the layout freeze worth paying for?

Theory (7 min)
Rule
For a Client, the saving includes the opening date. Value a treatment on cost and delay together.
How it is built
  • Net benefit = Drop in probability × (cost + delay) − Offer
Usual mistake
Only the construction cost counted. A layout change also delays opening; add the delay cost.
At work
Clients buy treatments (surveys, design freezes, early utility orders) when they save more than they cost, delay included.

Back to the course