Course introduction · 3 min

Design management (UK)

You manage the design for the main contractor on a two-storey health centre. The first-floor slab is weeks away and the models do not agree. In four tasks you raise the RFI that the slab depends on, price the wait when its reply is late, date five clash topics from the programme and close only what the re-run proves.

Start task 1

The health centre site with its concrete frame going up.Fictional project
Ashbrook Community Health CentreTwo-storey health centre · March 2027
Building
Two-storey community health centre, concrete slabs, masonry walls
What you manage
The questions to the designers and the clash topics before the first-floor slab
Rules
NEC4 ECC clauses 13.3, 15.1, 60.1(6); BCF 3.0; CDM 2015
Work in the ERP
4 tasks, about 1 h 7 min

Who hands what to whom

Every arrow is a question, an answer or a topic that crosses your desk, and the task where that happens.

Comes to you

  • M&E designerYour own design team
    • Clash in the riserTask 1
    • ReroutesTask 4
  • Structural engineerThe Client's designer
    • Answer to RFI-001Task 4
    • Beam openingsTask 3
YouDesign manager, main contractor

Goes from you

    • RFI-001Task 1
    • Slip and costTask 2
    Project ManagerAnswers for the Client
    • Due datesTask 3
    • Clear to buildTask 4
    Site managerRuns the slab

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks on one question and its clock, two on the clash topics. Start with task 1: in RFI you raise the question the slab depends on.

  1. The question

    Task 1 · 12 min

    RFI-001: the riser pipes and the slab

    You produce
    RFI-001 open with its reply date and priority
    Document
    The clash in the riser
    In the ERP
    RFI
  2. The question

    Task 2 · 15 min

    The reply is late: put a price on the wait

    You produce
    The slip and the cost of the late reply on RFI-001
    Document
    The Project Manager's promise
    In the ERP
    RFI
  3. The clashes

    Task 3 · 20 min

    Five clash topics: due dates from the programme

    You produce
    Five clash topics with due dates and priorities
    Document
    Clash run R1
    In the ERP
    Model Issues
  4. The clashes

    Task 4 · 20 min

    Close only what the re-run proves

    You produce
    RFI-001 closed and the topics closed or reopened on the re-run
    Document
    Update R2 and the re-run
    In the ERP
    RFI, Model Issues

From a clash to a slab you can pour

Each step below is one task. The design file grows: the question, its clock, the cost of waiting, and the topics closed on evidence.

RFI open
Task 1AskRFI to the Project Manager, with its reply date.
ExposureRFI
Task 2PriceSlip and cost of the late reply on the record.
Topics dated
Task 3DateEvery topic due before the work that builds its fix.
Still openClosed
Task 4CloseClosed on the re-run, not on the comment.

Blue is what the task adds; grey is carried over from before.

In short. Every question has a reply date. Price a late one. Date each fix from the programme. Close on evidence.