Course introduction · 3 min
Design management (UK)
You manage the design for the main contractor on a two-storey health centre. The first-floor slab is weeks away and the models do not agree. In four tasks you raise the RFI that the slab depends on, price the wait when its reply is late, date five clash topics from the programme and close only what the re-run proves.
Fictional project- Building
- Two-storey community health centre, concrete slabs, masonry walls
- What you manage
- The questions to the designers and the clash topics before the first-floor slab
- Rules
- NEC4 ECC clauses 13.3, 15.1, 60.1(6); BCF 3.0; CDM 2015
- Work in the ERP
- 4 tasks, about 1 h 7 min
Who hands what to whom
Every arrow is a question, an answer or a topic that crosses your desk, and the task where that happens.
Comes to you
- M&E designerYour own design team
- Clash in the riserTask 1
- ReroutesTask 4
- Structural engineerThe Client's designer
- Answer to RFI-001Task 4
- Beam openingsTask 3
YouDesign manager, main contractorGoes from you
- RFI-001Task 1
- Slip and costTask 2
- Due datesTask 3
- Clear to buildTask 4
Site managerRuns the slab
The project and the people are fictional. Portraits are generated.
Your route through the job
Two tasks on one question and its clock, two on the clash topics. Start with task 1: in RFI you raise the question the slab depends on.
The question
Task 1 · 12 min
RFI-001: the riser pipes and the slab
- You produce
- RFI-001 open with its reply date and priority
- Document
- The clash in the riser
- In the ERP
- RFI
The question
Task 2 · 15 min
The reply is late: put a price on the wait
- You produce
- The slip and the cost of the late reply on RFI-001
- Document
- The Project Manager's promise
- In the ERP
- RFI
The clashes
Task 3 · 20 min
Five clash topics: due dates from the programme
- You produce
- Five clash topics with due dates and priorities
- Document
- Clash run R1
- In the ERP
- Model Issues
The clashes
Task 4 · 20 min
Close only what the re-run proves
- You produce
- RFI-001 closed and the topics closed or reopened on the re-run
- Document
- Update R2 and the re-run
- In the ERP
- RFI, Model Issues
From a clash to a slab you can pour
Each step below is one task. The design file grows: the question, its clock, the cost of waiting, and the topics closed on evidence.
Blue is what the task adds; grey is carried over from before.
In short. Every question has a reply date. Price a late one. Date each fix from the programme. Close on evidence.