All 4 tasks freeIntermediate1 h of studyUnited Kingdom · NEC4 ECC Option B
Design management (UK)
Keep the design ahead of the first-floor slab of a health centre as the main contractor's design manager: raise the RFI for riser pipes the structure has no opening for, price the wait when the reply is late, give five clash topics their due dates from the programme, and close only what the clash re-run proves.

Who this course is for


The project and people are invented for training. The rules and contract forms are real.
You will be able to
Skills checked
- Raise an RFI to the right party and set its reply date from the contract period
- Count the working days a late reply takes from the programme and price the wait
- Give each clash topic a due date and priority from the work it must precede
- Close clash topics on the evidence of a re-run, not on a designer's comment
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Certificate
Awarded when all 4 tasks pass the numbers, trace and explain checks.

Files you work with
Created in your OpenConstructionERP workspace the moment you enrol.
- parties4 records
- Documentsdrawings and model2 files
What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses

Your roleContractor's commercial manager (quantity surveyor)
Interim payment assessment (UK, NEC4 Option B)
Price an NEC4 Option B assessment on a health centre new build: the Y(UK)2 and Construction Act timetable, the Price for Work Done to Date with X16 retention, pay less notices and VAT.
Intermediate2 h of studyFigures checked 14EN
All 4 tasks freeCertificate of completion

Your roleContractor's BIM coordinator (information manager)
BIM coordination and clash detection (UK, ISO 19650)
Coordinate a health centre's design models the ISO 19650 way: choose what goes into the federated model, set clash runs from the BEP clash matrix, triage hard and clearance clashes and duplicates.
Intermediate2 h of studyFigures checked 12EN
All 4 tasks freeCertificate of completion

Your roleSustainability / cost consultant preparing an upfront carbon estimate
Upfront carbon A1-A5 (UK)
Estimate the upfront carbon A1-A5 of a new health centre's frame, slabs and walls, and use it to decide: which wall swap cuts carbon per m², which nearer supplier cuts transport most.
Intermediate2 h of studyFigures checked 18EN
All 5 tasks freeCertificate of completion