Theory before task 1 · 8 min

The RFI and its period for reply

RFI-001: the riser pipes and the slab

Course introduction

After this lecture you can

  1. Raise an RFI to the right person when the Client's design has a gap.
  2. Set the reply date from the period for reply in the contract.
  3. Count the working days a reply leaves before the work it holds up.
1 / 4

What an RFI is for

A request for information asks a designer to close a gap or settle a conflict in the design you have to build. On an NEC4 Option B job the architect and the structural engineer work for the Client, so a question about their design goes to the Project Manager, who answers or gets the answer. A question about your own design, such as the M&E routes, is settled inside your team.

Example. Here the riser pipes are your design; the slab they pass through is the Client's.
2 / 4

The period for reply

NEC4 ECC clause 13.3 sets a period for reply in the Contract Data for any reply the contract asks for. In this contract it is two weeks. Put the reply date on the RFI when you raise it: it turns 'we are still waiting' into a date that has either passed or not.

Example. Two weeks is calendar time; the designer works in working days.
Period for reply, calendar days14
Weekend days in it4
Working days the designer has, with no bank holiday10
3 / 4

Days in hand

What matters on site is how many working days lie between the reply date and the day the work needs the answer. Weekends and bank holidays are not working days. If the redesign needs more than you have, the work waits; if it needs fewer, the rest is float.

Example. Easter can take two days out of a fortnight before a pour.
Common mistake

Counting weekdays, not working days

Counting Monday to Friday on a calendar feels like counting working days, until a bank holiday sits in the window. In spring there are four: Good Friday, Easter Monday and two in May. Check the official list before you count.

Example. A window that looks like seven days can be five.

An RFI on the roof-slab upstands

Same job, a later question: the upstand detail at the roof slab RS1.

Not to scale
The problem
  • Reply due Monday 10 May 2027; RS1 formwork starts Friday 21 May.
  • Calendar days strictly between them: 10, of which 2 are a weekend; no bank holiday falls in the window.
  • The engineer needs 3 working days to issue the drawing.
Step 1 of 2

Days in hand

How many working days lie between the reply and the formwork?

10 − 2 = 8.

Step 2 of 2

Float

How many working days of float are left after the drawing?

8 − 3 = 5.

In short. Reply date from the contract, then working days to the work, then what the redesign uses.

Check yourself

Question 1 of 2

Who answers a question about the Client's structural design under NEC4 Option B?

  • Right.

  • The slab is not your design.

  • A design gap is not settled on site.

  • They build the design; they do not own it.

Question 2 of 2

A reply is due on a Thursday; the work starts the Thursday after next. No bank holidays. How many working days lie strictly between?

Friday to the next-but-one Wednesday: 9 calendar days, 2 weekend days, 7 working days.

Read the source