Theory before task 2 · 9 min

When the reply is late: early warning and the cost of waiting

The reply is late: put a price on the wait

After this lecture you can

  1. Give an early warning as soon as a late reply threatens the work.
  2. Work out how many working days a late reply moves the work.
  3. Price the wait at time-related Defined Cost.
1 / 4

Early warning first

NEC4 clause 15.1 asks both the Contractor and the Project Manager to give an early warning as soon as they become aware of a matter that could delay Completion or raise the Prices. A missed reply date is exactly that. The warning goes in the day after the date passes, with what is held up.

Example. One line to the Project Manager the morning after the reply date.
2 / 4

A late reply is a compensation event

Under clause 60.1(6) a reply from the Project Manager that is not given within the time the contract requires is a compensation event. The Contractor notifies it within eight weeks of becoming aware (61.3). Under Option B it is assessed on Defined Cost plus the fee, against the programme.

Example. The record you make now is what the assessment is built from later.
3 / 4

Only the days that reach the work

A reply five working days late does not always cost five days. Float between the reply date and the work takes up part of it; the drawing still takes its own time after the answer. The slip is the number of working days the work's start moves.

Example. Another reply on the same job: four days late, one day of float.
£41−£12£33
  • 1 Reply late, working days
  • 2 Float taken up
  • 3 Slip at the work
Common mistake

Pricing the wait at the bill rate

The bill has a weekly rate for preliminaries, and it is tempting to use it. Under Option B a compensation event is assessed on Defined Cost, the cost of the resources that actually wait. Use the time-related cost per working day; the fee is added in the assessment.

Example. Bill rates price the work in the tender; Defined Cost prices the change.

A late reply on the upstands

Same job, the roof-slab RFI from the last lecture, answered two working days after its float ran out.

Not to scale
The problem
  • Time-related Defined Cost while only the roof team waits: £2,750 a week, five working days.
  • RS1 formwork moves 2 working days.
Step 1 of 2

Per day

What does one working day of waiting cost?

£2,750 ÷ 5 = £550.00.

Step 2 of 2

Exposure

What is the exposure?

2 × £550.00 = £1,100.00.

In short. Slip in working days at the work, times Defined Cost per working day; fee later.

Check yourself

Question 1 of 2

The reply date passed yesterday with no answer. What do you do first?

  • Right: clause 15.1.

  • The warning is due as soon as you are aware.

  • The float may still cover it.

  • The engineer is the Client's designer.

Question 2 of 2

Time-related Defined Cost is £4,500 a week. The work moves 4 working days. What is the exposure before fee?

4,500 ÷ 5 × 4 = £3,600.00.

Read the source