Cheat sheet
Design management (UK)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- An RFI has a reply date. Count the working days it leaves before the work.
- How it is built
- Working days between the reply date and formwork = Weekdays after the reply, before formwork − Bank holidays
- Usual mistake
- You counted Monday to Friday and kept Good Friday and Easter Monday. Nobody issues a drawing on a bank holiday: leave them out.
- At work
- Design managers log every question to the designers with its reply date and the work it holds up.
- Rule
- Price the wait in working days of Defined Cost, and only the days that reach the work.
- How it is built
- Cost exposure on RFI-001 = Schedule slip (days) × Weekly time-related cost ÷ 5
- Usual mistake
- That is a full week of time-related cost. Count the working days formwork moves, from its planned start to its new one.
- At work
- When a reply is late the design manager gives an early warning and records the slip and its cost the same day.
- Rule
- A fix is due before the work that builds it. Concrete waits for nobody.
- How it is built
- Topics that need the structural engineer = Topics whose fix changes concrete
- Usual mistake
- You sent the column topic to the engineer. Nobody cuts a hole in a column for a duct: the duct moves, in your own M&E design.
- At work
- After every clash run the design manager dates and prioritises the topics against the programme.
- Rule
- Resolved is a claim; the re-run is the evidence. Close only what it shows clear.
- How it is built
- Topics closed = Topics the re-run shows clear
- Usual mistake
- You closed every topic marked Resolved. The pipe topic is still a clash on the re-run: 50 mm is inside the rule.
- At work
- Design managers close clash topics only against a re-run of the updated models, never on a designer's word.