Course introduction · 3 min

Document control in a CDE (UK)

You are the main contractor's document controller on a two-storey health centre in England: the person who makes sure everyone builds from the right drawing. In four tasks you follow the first-floor slab's drawings from a fabricator's cutting list to a construction issue, and check a subcontractor's names against the project standard.

Start task 1

The health centre's two-storey brick frame in scaffolding and green netting, with workers on the access road.Fictional project
Ashbrook Community Health CentreDocument control · March 2027
Contract
NEC4 Engineering and Construction Contract, Option B
Standard
BS EN ISO 19650-2 with the UK National Annex; the project information standard
Package
First floor slab FS1: the rebar on four structural drawings
Work in the ERP
4 tasks, about 1 h 2 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • The engineerStructural engineer
    • S-2103 P01 by e-mailTask 1
    • C01 of S-2101 and S-2103Task 2
  • Steel supplierRebar fabricator
    • Cutting list FS1Task 1
  • The masonry subMasonry subcontractor
    • Six shop drawingsTask 4
YouDocument controller

Goes from you

    • Transmittal for constructionTask 2
    Supplier and fixerCut and fix the steel
    • C01 by transmittalTask 3
    Other P02 holdersSite, temporary works, QS
    • Names returnedTask 4
    The masonry subMasonry subcontractor

The project and the people are fictional. Portraits are generated.

Your route through the job

Start with task 1: in the Common Data Environment you find which steel was cut from drawings nobody authorised.

  1. Authority

    Task 1 · 12 min

    Steel cut from an S2 drawing

    You produce
    Steel at risk on FS1
    Document
    The steel supplier's cutting list
    In the ERP
    Common Data Environment
  2. Authority

    Task 2 · 20 min

    Authorise and issue for construction

    You produce
    C01 published and issued for construction
    Document
    Transmittal
    In the ERP
    Common Data Environment, Transmittals
  3. Distribution

    Task 3 · 15 min

    Every holder of P02 gets C01

    You produce
    Every P02 holder on C01
    Document
    Distribution log
    In the ERP
    Transmittals
  4. Standard

    Task 4 · 15 min

    File names that break the standard

    You produce
    The subcontractor's valid names registered for review
    Document
    Submission GMS-T-004
    In the ERP
    Common Data Environment

How a drawing becomes steel in the slab

Each step below is one task, in the order the information moves.

At riskA1
Task 1AuthorityOnly Published A1 may be built from. On the register is not enough.
TransmittedPublished
Task 2IssuePublish with a signature, then transmit with a record.
Still on P02Sent
Task 3SupersedeEvery holder of the old revision gets the new one.
ReturnedRegistered
Task 4StandardNames are data: check them field by field.

Blue is what the task adds; grey is carried over from before.

In short. Build only from Published A1. Issue by transmittal. Close every old distribution. Return bad names.