Theory before task 1 · 7 min

States and status codes: what may be built from

Steel cut from an S2 drawing

Course introduction

After this lecture you can

  1. Name the four CDE states and say what each allows.
  2. Read a suitability code and say whether work may start from it.
  3. Find the quantities that rest on drawings not authorised for construction.
1 / 3

Four states, one direction

ISO 19650 puts every piece of project information in one of four states. Work in progress is the author's own. Shared is offered to others to coordinate, inform or review. Published is authorised for use, such as construction. Archived keeps the history. A container moves forward through approval gates; it never slides back quietly.

Example. On this project the engineer's slab drawing sits in Shared while the architect checks the voids, then moves to Published once it is signed off.
Work in progressS0, author only
SharedS1 to S4
PublishedA1 and up
Archivedhistory
2 / 3

The code says what the drawing is for

The UK National Annex to ISO 19650-2 gives each shared or published container a status code. S1 is for coordination, S2 for information, S3 for review and comment, S4 for stage approval. A codes mean authorised. The project information standard (our case) sets A1 as authorised for construction. The revision matters too: P01, P02 are preliminary; C01 is the first contractual revision.

Common mistake

On the register means approved

A drawing on the register looks official, so fabricators and site teams use it. But Shared S2 means for information: the engineer may still change it. The check is the state and the code together, every time, before a cutting list, an order or a pour.

Example. Ask for the drawing number, revision and code on every cutting list, and check them against the register the day it arrives.

Steel on a mixed list

Different numbers from your task.

Not to scale
The problem
  • A rebar list cites three drawings: 1.9 t from a Shared S3 drawing, 4.1 t from Published A1, 0.7 t from a drawing only e-mailed.
Step 1 of 2

Authorised

How many tonnes rest on authorised drawings?

Only the A1 drawing is authorised: 4.1 t.

Step 2 of 2

At risk

How many tonnes are at risk?

1.9 + 0.7 = 2.6 t.

In short. Anything not Published A1, on the register or not, is at risk.

Check yourself

Question 1 of 3

A drawing is Shared with code S2. May the fixer work from it?

  • Being on the register is not authority.

  • Right: only Published A codes authorise use.

  • P revisions are preliminary.

Question 2 of 3

Which revision is the first contractual one?

  • P marks preliminary.

  • Right: C marks contractual.

  • That is a status code, not a revision.

Question 3 of 3

A list cites 2.2 t on Published A1 and 1.3 t on Shared S4. How many tonnes are at risk?

S4 is still Shared: 1.3 t is at risk.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.