Theory before task 2 · 7 min

Authorise, then transmit

Authorise and issue for construction

After this lecture you can

  1. Describe the Shared-to-Published approval gate and who signs it.
  2. Say why a transmittal is the record of issue.
  3. Count working days to a delivery with bank holidays in the way.
1 / 3

The approval gate

Moving a container from Shared to Published is an approval. ISO 19650-2 has the lead appointed party authorise information before it is published (clauses 5.7 and 5.8, paraphrased). In the ERP that is Promote: the Gate B dialog asks for your signature and a comment, and the CDE keeps them with the container.

Example. On this project you sign for the main contractor once the engineer's C01 has arrived and been linked to its container.
2 / 3

A transmittal proves the issue

Publishing makes a drawing available; it does not put it in anyone's hands. A transmittal lists what was sent, to whom, for what purpose and when. NEC4 clause 13 asks for communications in a form that can be read, copied and recorded: a transmittal is exactly that record.

Link Documentfile to container
Promote, Gate Bsigned
New TransmittalFor Construction
Issuedated record
Common mistake

Forgetting the calendar

A supplier's lead time is in working days. Weekends and bank holidays are not. Easter takes out a Friday and a Monday together, so a four-day gap in March can hold only two working days. Count from the official list, not from memory.

Example. Write the delivery date and the last day to issue on the transmittal's cover note.

Working days over a bank holiday

Different dates from your task.

Not to scale
The problem
  • Issue on a Tuesday; delivery the next Tuesday, 7 calendar days later. The Monday is a bank holiday.
Step 1 of 2

Take out the weekend

Days left without Saturday and Sunday?

7 − 2 = 5.

Step 2 of 2

Take out the bank holiday

Working days to delivery?

5 − 1 = 4, the delivery day counted.

In short. Calendar days less weekends less bank holidays.

Check yourself

Question 1 of 3

What does Gate B in the ERP record?

  • Right.

  • E-mail is not the register.

  • That would be a reply to the transmittal.

Question 2 of 3

Why issue by transmittal after publishing?

  • Right.

  • It is allowed; the order is your discipline.

  • It changes nothing on the container.

Question 3 of 3

Issue on Thursday 23 December; delivery Thursday 30 December. 25-28 December are a weekend and two bank holidays. Working days, delivery day counted?

24, 29 and 30 December: 3 working days.

Read the source