Theory before task 3 · 6 min

Superseding a revision

Every holder of P02 gets C01

After this lecture you can

  1. Say what happens to holders of a superseded revision.
  2. Tell a holder from the originator.
  3. Close a distribution from the log.
1 / 3

Superseded is not deleted

When C01 replaces P02 in the CDE, P02 moves to the history. But the paper and PDF copies of P02 are still on desks and in site cabins. ISO 19650 relies on the CDE being the single source; that only works if everyone who took a copy of the old revision is given the new one.

Example. The site manager pins the slab drawing in the cabin. If nobody sends C01, the old laps get fixed.
2 / 3

The distribution log is the list

Every transmittal adds names to a revision's distribution. When a revision is superseded, take the old distribution, strike off who already has the new one, and issue to the rest the same day. The originator wrote the new revision and is not a holder.

£51−£22£33
  • 1 Held P02
  • 2 Sent C01 already
  • 3 Still to send
Common mistake

Sending only to the people who build

It is tempting to send a structural revision to the fixer and stop. The cost consultant measures from it, the temporary works coordinator designs props around it. Anyone who held the old revision can act on it.

Example. Keep the log open while you fill in the recipients, and tick each name.

Closing a distribution

Different numbers from your task.

Not to scale
The problem
  • An architect's plan went to 7 holders at P03. The P04 issue has already gone to 3 of them.
Step 1 of 1

Still on P03

How many holders still need P04?

7 − 3 = 4.

In short. Old distribution less new distribution is who still needs it.

Check yourself

Question 1 of 2

The engineer issued P02 and now C01. Is the engineer a holder you must send C01 to?

  • Right.

  • The originator wrote it; it is not a recipient.

  • It already holds C01.

Question 2 of 2

Why send C01 to the cost consultant?

  • Right.

  • It does not.

  • One is enough.