Course introduction · 3 min

Hold points and non-conformance reports (UK)

You are the contractor's quality manager on a two-storey health centre in England. On a Monday morning the first-floor slab is poured before anyone released the reinforcement check. In five tasks you take that one failure from the first record to a closed NCR: what is in doubt, how bad it is, why it happened, what it costs and who pays for the repeat test.

Start task 1

The health centre's two-storey frame on site, with scaffolding and the first-floor slab edge.Fictional project
Ashbrook Community Health CentreFirst-floor slab FS1 · April to May 2027
Slab
FS1, the 250 mm first-floor slab, poured in one go on Monday 19 April 2027
Contract
NEC4 Engineering and Construction Contract, Option B (priced contract with bill of quantities)
Records
Inspections and Non-conformance in the ERP, one NCR from start to close
Work in the ERP
5 tasks, about 1 h 20 min

Who hands what to whom

Every arrow is a record or a decision that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site teamPoured FS1
    • A blank hold-point sheetTask 1
  • Structural engineerAccepts or repairs
    • Acceptance and the soffit repairTask 3
YouQuality manager, main contractor

Goes from you

    • NCR-001 and the surveyTask 2
    • The re-inspectionTask 5
    SupervisorChecks the works for the Client
    • The cost of NCR-001Task 4
    Commercial managerRuns the cost report

The project and the people are fictional. Portraits are generated.

Your route through the job

One record, then the NCR from start to close. Start with task 1: in Inspections you record the hold point as it stands and measure what is in doubt.

  1. Record

    Task 1 · 10 min

    A pour past an unreleased hold point

    You produce
    The failed hold point and the concrete in doubt
    Document
    Inspection INS-001
    In the ERP
    Inspections
  2. Record

    Task 2 · 15 min

    NCR-001 and the cover survey

    You produce
    NCR-001, graded from the cover survey
    Document
    Covermeter survey
    In the ERP
    Non-conformance
  3. Understand

    Task 3 · 20 min

    Root cause, and what it does to the programme

    You produce
    Root cause and the delay to masonry
    Document
    NCR-001
    In the ERP
    Non-conformance
  4. Understand

    Task 4 · 20 min

    The cost of putting it right

    You produce
    The cost of NCR-001
    Document
    NCR-001 cost impact
    In the ERP
    Non-conformance
  5. Close

    Task 5 · 15 min

    Re-inspect, pay for the repeat test, close NCR-001

    You produce
    Re-inspection, repeat-test cost, NCR closed
    Document
    Inspection INS-002
    In the ERP
    Inspections, Non-conformance

How a skipped check turns into cost

Each step below is one task, in the order the problem unfolds.

UnprovenPoured
Task 1The hold pointWork that covers a hold point before it is released puts everything under it in doubt.
Below coverAccepted
Task 2The NCRA survey turns doubt into evidence; the NCR is graded on it.
DelayPlanned
Task 3Root causeFind the process step that let it happen, and what the delay does to the programme.
TimeRepair
Task 4Cost of reworkDirect cost plus standing time, all of it at the Contractor's risk.
Repeat costVerified
Task 5CloseRe-inspect, pay the Client's repeat cost, change the process before the next pour.

Blue is what the task adds; grey is carried over from before.

In short. Release the hold point before the work covers it. If it was missed, record it honestly, prove the product, fix the process.