Course introduction · 3 min
Hold points and non-conformance reports (UK)
You are the contractor's quality manager on a two-storey health centre in England. On a Monday morning the first-floor slab is poured before anyone released the reinforcement check. In five tasks you take that one failure from the first record to a closed NCR: what is in doubt, how bad it is, why it happened, what it costs and who pays for the repeat test.
Fictional project- Slab
- FS1, the 250 mm first-floor slab, poured in one go on Monday 19 April 2027
- Contract
- NEC4 Engineering and Construction Contract, Option B (priced contract with bill of quantities)
- Records
- Inspections and Non-conformance in the ERP, one NCR from start to close
- Work in the ERP
- 5 tasks, about 1 h 20 min
Who hands what to whom
Every arrow is a record or a decision that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site teamPoured FS1
- A blank hold-point sheetTask 1
- Structural engineerAccepts or repairs
- Acceptance and the soffit repairTask 3
YouQuality manager, main contractorGoes from you
- NCR-001 and the surveyTask 2
- The re-inspectionTask 5
- The cost of NCR-001Task 4
The project and the people are fictional. Portraits are generated.
Your route through the job
One record, then the NCR from start to close. Start with task 1: in Inspections you record the hold point as it stands and measure what is in doubt.
Record
Task 1 · 10 min
A pour past an unreleased hold point
- You produce
- The failed hold point and the concrete in doubt
- Document
- Inspection INS-001
- In the ERP
- Inspections
Record
Task 2 · 15 min
NCR-001 and the cover survey
- You produce
- NCR-001, graded from the cover survey
- Document
- Covermeter survey
- In the ERP
- Non-conformance
Understand
Task 3 · 20 min
Root cause, and what it does to the programme
- You produce
- Root cause and the delay to masonry
- Document
- NCR-001
- In the ERP
- Non-conformance
Understand
Task 4 · 20 min
The cost of putting it right
- You produce
- The cost of NCR-001
- Document
- NCR-001 cost impact
- In the ERP
- Non-conformance
Close
Task 5 · 15 min
Re-inspect, pay for the repeat test, close NCR-001
- You produce
- Re-inspection, repeat-test cost, NCR closed
- Document
- Inspection INS-002
- In the ERP
- Inspections, Non-conformance
How a skipped check turns into cost
Each step below is one task, in the order the problem unfolds.
Blue is what the task adds; grey is carried over from before.
In short. Release the hold point before the work covers it. If it was missed, record it honestly, prove the product, fix the process.