Theory before task 1 · 8 min

Hold points, witness points and what a missed one costs

A pour past an unreleased hold point

Course introduction

After this lecture you can

  1. Tell a hold point from a witness point and say who releases each.
  2. Say what a pour past an unreleased hold point puts in doubt.
  3. Calculate the concrete volume in doubt from the slab area with voids deducted.
1 / 3

An inspection and test plan in four lines

An inspection and test plan (ITP) lists each check on a piece of work, when it happens, who signs it and whether the work may go on without it. A hold point stops the work: nothing covers it until someone named releases it. A witness point is offered to the client's side to watch, but the work goes on if nobody comes. On this job the FS1 plan has two of each.

Example. Read a hold point as a locked gate with one key holder. On this job the key for H2 is the section engineer's signature, and the Supervisor is told 24 hours before.
H1 Formwork and falsework, permit to loadhold
H2 Reinforcement before the pourhold
W1 Delivery tickets and slumpwitness
W2 Test cubes takenwitness
2 / 3

What a missed hold point puts in doubt

Once concrete covers the steel, the check H2 was meant to make can no longer be made by eye. The steel may be perfect, but nobody can prove it. Everything poured over it is in doubt until a survey or an engineer says otherwise. That is why the first record is the volume of concrete over unchecked steel, measured as poured: the slab area with its voids deducted, times its thickness.

Example. A stair void holds no concrete and no steel, so it holds no doubt either.
Gross slab area
186.00 m²
Voids (not poured)
6.00 m²
Area poured
180.00 m²
Common mistake

Signing the sheet after the pour

The easy fix is to sign H2 on Monday afternoon, since the fixers say the steel was right. That records a check that never happened, and it hides the real problem: the pour could start without the key holder. Record H2 as failed, raise the nonconformity, and let the evidence decide the steel.

Example. A late signature looks like a release. A failed record with a survey behind it is what a client's auditor trusts.

The volume in doubt

Different numbers from your task.

Not to scale
The problem
  • A slab of gross area 186.00 m² has voids of 6.00 m².
  • It is 0.2 m thick and was poured in one go past its reinforcement hold point.
Step 1 of 2

Area poured

What area was actually poured?

186.00 m² − 6.00 m² = 180.00 m².

Step 2 of 2

Volume

How many cubic metres sit over unchecked steel?

180.00 m² × 0.2 m = 36 m³.

In short. Net area times thickness: the concrete that now needs proof.

Check yourself

Question 1 of 3

Nobody from the client's side came to witness the cube sampling. May the pour go on?

  • Right. A witness point is offered; a hold point stops.

  • Only hold points stop the work.

  • Nobody signs for an absent witness; the work simply goes on.

Question 2 of 3

H2 was never released and the slab is poured. What do you record first?

  • That records a check that never happened.

  • Right. The record shows the process failed; the survey will show whether the product did.

  • Cubes test the concrete, not the steel under it.

Question 3 of 3

A 300 mm slab has a net area of 120.00 m² and was poured past its hold point. How many m³ are in doubt?

120.00 × 0.3 = 36 m³.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.