OpenConstruction Academy
Sign in / Register
EN

Course introduction · 3 min

Getting paid as a subcontractor (UK, Construction Act)

You are the quantity surveyor for the masonry subcontractor on a two-storey health centre in England: the person who makes sure the firm is paid for the walls it builds. In five tasks you follow one subcontract from a short payment to a notice of adjudication, using the payment rules of the Construction Act.

Start task 1

The health centre's two-storey brick frame in scaffolding and green netting, with workers on the access road.Fictional project
Ashbrook Community Health CentreMasonry subcontract · February to June 2027
Package
Brick and block walls, four lines priced per square metre
Subcontract
A bespoke subcontract with monthly applications and 3 % retention
Law
Housing Grants, Construction and Regeneration Act 1996, as amended in 2009
Work in the ERP
5 tasks, about 1 h 27 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Main contractorPays your applications
    • A short paymentTask 1
    • A late pay less noticeTask 2
    • Site instruction SI-07Task 4
YouSubcontractor's quantity surveyor

Goes from you

    • Applications 1 to 3Task 3
    • Variation SV-01Task 4
    Main contractor's QSValues your applications
    • Notice of adjudicationTask 5
    AdjudicatorDecides within 28 days

The project and the people are fictional. Portraits are generated.

Your route through the job

Three tasks on getting paid, one on a change, one on a dispute. Start with task 1: in Contracts you submit application 1 and find what is still owed.

  1. Getting paid

    Task 1 · 12 min

    Paid short with no notice: what is still owed

    You produce
    What is still owed after a short payment
    Document
    Application 1 and the payment record
    In the ERP
    Contracts, Progress Claims
  2. Getting paid

    Task 2 · 15 min

    A pay less notice one day late

    You produce
    The sum payable despite a late pay less notice
    Document
    Application 2 and the pay less notice
    In the ERP
    Contracts, Progress Claims
  3. Getting paid

    Task 3 · 20 min

    Application 3: carry the shortfall forward

    You produce
    Application 3, with the shortfall carried
    Document
    Cumulative application
    In the ERP
    Contracts, Progress Claims
  4. Change

    Task 4 · 20 min

    SI-07: price and submit a subcontract variation

    You produce
    Variation SV-01, priced and submitted
    Document
    Site instruction SI-07
    In the ERP
    Variations, Requests
  5. Dispute

    Task 5 · 20 min

    Notice of adjudication for the unpaid sum

    You produce
    The sum claimed in a notice of adjudication
    Document
    Notice of adjudication
    In the ERP
    Contracts, Progress Claims

How a wall becomes money in the bank

Each step below is one task, in the order the money moves.

ShortPaid
Task 1The notified sumAn application made on time is the sum due. Without a notice from the payer, all of it is paid by the final date.
Late notice: no effectNotified sum
Task 2Pay less noticesThe payer may pay less only with a written notice, in time, that says how much and why.
Applied forRetentionPaid before
Task 3Cumulative applicationEach month value all work to date, hold retention, and take off what was actually paid.
Cost plusAt rates
Task 4VariationsChanged work is priced at subcontract rates where it is similar, at cost plus where it is new.
Interest and fixed sumDebt
Task 5AdjudicationAn unpaid sum goes to an adjudicator, with statutory interest and a fixed sum on top.

Blue is what the task adds; grey is carried over from before.

In short. Apply on time. Pay the notified sum unless a valid notice came in time. Claim what was not paid, once.