Theory before task 1 · 8 min

The notified sum and the payment clock

Paid short with no notice: what is still owed

Course introduction

After this lecture you can

  1. Name the four dates of a payment cycle and say which notice belongs to each.
  2. Say why an application made on time becomes the sum the payer must pay.
  3. Calculate what is still owed after a part payment with no notice.
1 / 3

Four dates for every payment

The Construction Act makes every construction contract say how much is due and when. Each payment has a due date, a deadline for the payer's payment notice, a deadline for a pay less notice, and a final date by which the money must be in the bank. Here the subcontract counts them from your application on the 22nd.

Example. Write all four dates in your diary the day you apply. Each one is a deadline for the other side, not for you.
Applicationday 0
Due dateday 7
Payment notice, latestday 12
Pay less notice, latestday 21
Final date for paymentday 28
2 / 3

The notified sum

If the payer gives no payment notice, a subcontract like this one treats your application, made on time, as the notice of the sum due. That figure is the notified sum. By the final date the payer must pay all of it, less only what a valid pay less notice allows. Retention comes off before that: the application states the sum after the 3 per cent is held.

Common mistake

Accepting a round number

A payment of a round sum with no paperwork often feels like a settlement. It is not. Without a notice in time, the gap between the notified sum and the money received is a debt, payable from the final date, and statutory interest runs on it.

Example. Reply in writing the same week: the notified sum, what arrived, and what is still owed.

From application to shortfall

Different numbers from your task.

Not to scale
The problem
  • An application made on time for a gross of £10,000.00, retention 3%.
  • No payment notice, no pay less notice. On the final date £6,500.00 arrives.
Step 1 of 3

Retention

How much retention is held?

£10,000.00 × 3% = £300.00.

Step 2 of 3

Notified sum

What is the notified sum?

£10,000.00 − £300.00 = £9,700.00. No notice came, so this is due in full.

Step 3 of 3

Still owed

How much is still owed?

£9,700.00 − £6,500.00 = £3,200.00, a debt from the final date.

In short. Gross less retention is the notified sum; less what arrived is the debt.

Check yourself

Question 1 of 3

The payer sends no payment notice and no pay less notice. What must it pay by the final date?

  • Its view counts only through a notice in time.

  • Right: HGCRA s111.

  • Nothing in the Act or the subcontract splits it.

Question 2 of 3

Which date does the pay less notice deadline hang from?

  • Only the due date runs from the application here.

  • That is the payment notice.

  • Right: not later than the set number of days before it.

Question 3 of 3

Notified sum 8,400.00. On the final date 5,000.00 arrives, with no notice. How much is still owed?

8,400.00 − 5,000.00 = 3,400.00.