Theory before task 2 · 8 min

Pay less notices: time first, then content

A pay less notice one day late

After this lecture you can

  1. Say what a valid pay less notice must contain.
  2. Count the pay less deadline back from the final date.
  3. Work out the sum payable when a notice comes too late.
1 / 3

What a valid notice contains

A pay less notice is in writing. It states the sum the payer considers due on the date of the notice and the basis on which that sum is calculated. A notice that only says 'we are deducting cleaning costs' with no figure, or arrives too late, is not a valid pay less notice.

2 / 3

Counting the deadline

The Act ties the pay less deadline to the final date: not later than the period the contract sets before it. In this subcontract that is 7 days. Count back from the final date, then compare the date the notice arrived.

Example. A notice dated 24 June against a final date of 30 June is one day late.
Final date for payment30 June
Less the period7 days
Last day for the notice23 June
Common mistake

Arguing the reason first

Teams often debate whether a contra charge is fair before checking the notice's date. If the notice is late, the reason does not matter for this payment: the notified sum is payable. The charge itself is not lost; the payer can raise it in a later notice or a dispute.

Example. Answer a late notice in two lines: it was late, so the notified sum is due; the charge can be discussed separately.

A notice tested on its date

Different numbers from your task.

Not to scale
The problem
  • Notified sum £14,600.00. Final date: day 30 of June.
  • A pay less notice for £1,200.00 arrives on 24 June.
Step 1 of 2

Deadline

Last day of June for a valid notice?

30 − 7 = 23: 23 June. The notice on 24 June is late.

Step 2 of 2

Sum payable

What must be paid by the final date?

The notified sum stands: £14,600.00.

In short. Date first. A late notice leaves the notified sum untouched.

Check yourself

Question 1 of 3

A notice arrives in time but gives no figure, only 'cleaning costs to follow'. Valid?

  • Time is one test; content is the other.

  • Right: HGCRA s111(4).

  • The figure must be in the notice.

Question 2 of 3

The notice is late. Is the payer's contra charge lost for good?

  • Only this deduction fails.

  • Right. It just cannot reduce this payment.

  • A late notice cannot reduce the notified sum.

Question 3 of 3

Notified sum 9,800.00. A pay less notice for 700.00 arrives one day after its deadline. What is payable?

The notice is late: 9,800.00 is payable.