Theory before task 3 · 9 min

Cumulative applications and the forgotten shortfall

Application 3: carry the shortfall forward

After this lecture you can

  1. Build an application from the value of all work to date.
  2. Say why the ERP's Net due differs from what you are owed after a short payment.
  3. Calculate the sum to apply for: gross to date, less retention, less payments received.
1 / 3

Value to date, every month

Each application values all the work done so far, not just this month's. Retention is held on that whole value. What comes off next depends on the subcontract: here it is the total of payments actually received.

£60,0001−£1,8002−£44,0003£14,2004
  • 1 Gross to date
  • 2 Retention to date
  • 3 Payments received
  • 4 Applied for
2 / 3

What the ERP's Net due means

The ERP builds each claim the way a certificate is built: cumulative value, less retention, less what earlier claims applied for. That is right when every claim was paid in full. When one was paid short, Net due no longer equals what you are owed, and the shortfall drops out unless you put it back.

Common mistake

Copying Net due

Copying the system's figure onto the application is the quickest way to lose a shortfall. Reconcile against the bank: what was received, not what was applied for. Then make sure the same pound is claimed once, either in the application or as a separate debt, never in both.

Example. Keep a one-line reconciliation under every application: gross to date, retention, received, applied for.

Putting the shortfall back

Different numbers from your task.

Not to scale
The problem
  • Gross to date £60,000.00; retention 3%.
  • Earlier applications, net: £46,000.00. Payments received: £44,000.00.
Step 1 of 3

Retention to date

Retention on the gross to date?

£60,000.00 × 3% = £1,800.00.

Step 2 of 3

ERP Net due

What does the ERP show as Net due?

£60,000.00 − £1,800.00 − £46,000.00 = £12,200.00.

Step 3 of 3

Sum applied for

What do you apply for?

£60,000.00 − £1,800.00 − £44,000.00 = £14,200.00: the shortfall is back in.

In short. Net due less earlier applications; your application less money received. The gap is the shortfall.

Check yourself

Question 1 of 3

Application 2 was paid in full; application 1 was paid short. Which figure hides the shortfall?

  • Gross does not depend on payments.

  • Right: it deducts what was applied for.

  • Retention follows the gross.

Question 2 of 3

The shortfall is in application 3. You also send a separate demand for it. What is wrong?

  • It asks for the same money twice.

  • Right. Claim each pound once.

  • A demand can come from you.

Question 3 of 3

Gross to date 40,000.00, retention 3 %, payments received 30,000.00. What do you apply for?

40,000.00 − 1,200.00 − 30,000.00 = 8,800.00.

Read the source