Getting paid as a subcontractor (UK, Construction Act)
Work as the masonry subcontractor's quantity surveyor on a health centre and get paid under the Construction Act: a short payment with no notice, a pay less notice one day late, a cumulative application that carries the shortfall, a variation priced and submitted, and a notice of adjudication with statutory interest.

Who this course is for


The project and people are invented for training. The rules and contract forms are real.
You will be able to
Skills checked
- Work out what is owed when no payment or pay less notice is given
- Test a pay less notice against the final date for payment
- Carry an unpaid shortfall into a cumulative application
- Price and submit a subcontract variation
- Claim statutory interest in a notice of adjudication
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5Notice of adjudication for the unpaid sumFoundation≈20 minTheory · 9 minCheat sheet: every rule on one page
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Videos on this method
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks.

Files you work with
Created in your OpenConstructionERP workspace the moment you enrol.
- parties4 records
- Billingcontract
What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses

Your roleContractor's commercial manager (quantity surveyor)
Interim payment assessment (UK, NEC4 Option B)
Price an NEC4 Option B assessment on a health centre new build: the Y(UK)2 and Construction Act timetable, the Price for Work Done to Date with X16 retention, pay less notices and VAT.
Intermediate2 h of studyFigures checked 14EN
All 4 tasks freeCertificate of completion

Your roleContractor's commercial manager (quantity surveyor)
Compensation events (UK, NEC4 ECC)
Quote, assess and implement compensation events under NEC4 ECC Option B on a health centre build: a Scope change priced with bill rates, a physical condition priced as Defined Cost plus Fee.
Advanced2 h of studyFigures checked 11EN
All 4 tasks freeCertificate of completion

Your roleMain contractor's QS
Tender to first valuation (UK, JCT)
You are the main contractor's QS on a four-storey shell-and-core office let under JCT SBC/Q 2024.
Foundation2 h of studyFigures checked 28EN
All 5 tasks freeCertificate of completion