Cheat sheet
Getting paid as a subcontractor (UK, Construction Act)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- No notice, no deduction. The payer pays the notified sum by the final date unless it gave a valid pay less notice in time.
- How it is built
- Still owed = Net due on application 1 − Paid on the final date
- Usual mistake
- The part payment accepted as settlement. With no notice in time, the shortfall stays a debt.
- At work
- Every month a subcontractor's QS checks each payment against the notified sum and chases any gap the same week.
- Rule
- A late notice changes nothing. Test the date of a pay less notice before its reason.
- How it is built
- Pay less deadline = Final date − 7 days
- Sum payable = Net due on application 2
- Usual mistake
- The late notice applied. A pay less notice after its deadline cannot reduce the notified sum.
- At work
- When a pay less notice arrives, the QS checks its date and content first, then answers its reasons.
- Rule
- Apply for what you are owed, not what the system expects. Payments received, not applications, come off.
- How it is built
- Sum applied for = Gross to date − Retention to date − Payments received
- Usual mistake
- The ERP's Net due typed. It takes off application 1 as applied for; add back what was never paid.
- At work
- Each monthly application is built cumulatively and reconciled against the bank, not against earlier applications.
- Rule
- Similar work at the subcontract rate, new work at cost plus. Never add overheads to a rate that already has them.
- How it is built
- Wall = Length × Height × MS-02 rate
- Fire-stopping = (Hours × rate + sealant) × 1.12 × Length
- SV-01 = Wall + Fire-stopping
- Usual mistake
- 12 % added to the wall too. The subcontract rate already includes overheads and profit.
- At work
- A subcontract QS prices every instruction within days, records it in the variation register and submits it.
- Rule
- One dispute, one clear sum. Debt, interest and the fixed sum, each with its basis.
- How it is built
- Interest = Shortfall × 11.75 % × Days ÷ 365
- Sum claimed = Shortfall + Interest + Fixed sum
- Usual mistake
- The fixed sum left out. The Act adds it to each late debt.
- At work
- Subcontractors use adjudication for unpaid notified sums; the notice states the dispute and the sum sought.