Cheat sheet

Getting paid as a subcontractor (UK, Construction Act)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Paid short with no notice: what is still owed

Theory (8 min)
Rule
No notice, no deduction. The payer pays the notified sum by the final date unless it gave a valid pay less notice in time.
How it is built
  • Still owed = Net due on application 1 − Paid on the final date
Usual mistake
The part payment accepted as settlement. With no notice in time, the shortfall stays a debt.
At work
Every month a subcontractor's QS checks each payment against the notified sum and chases any gap the same week.

Task 2

A pay less notice one day late

Theory (8 min)
Rule
A late notice changes nothing. Test the date of a pay less notice before its reason.
How it is built
  • Pay less deadline = Final date − 7 days
  • Sum payable = Net due on application 2
Usual mistake
The late notice applied. A pay less notice after its deadline cannot reduce the notified sum.
At work
When a pay less notice arrives, the QS checks its date and content first, then answers its reasons.

Task 3

Application 3: carry the shortfall forward

Theory (9 min)
Rule
Apply for what you are owed, not what the system expects. Payments received, not applications, come off.
How it is built
  • Sum applied for = Gross to date − Retention to date − Payments received
Usual mistake
The ERP's Net due typed. It takes off application 1 as applied for; add back what was never paid.
At work
Each monthly application is built cumulatively and reconciled against the bank, not against earlier applications.

Task 4

SI-07: price and submit a subcontract variation

Theory (9 min)
Rule
Similar work at the subcontract rate, new work at cost plus. Never add overheads to a rate that already has them.
How it is built
  • Wall = Length × Height × MS-02 rate
  • Fire-stopping = (Hours × rate + sealant) × 1.12 × Length
  • SV-01 = Wall + Fire-stopping
Usual mistake
12 % added to the wall too. The subcontract rate already includes overheads and profit.
At work
A subcontract QS prices every instruction within days, records it in the variation register and submits it.

Task 5

Notice of adjudication for the unpaid sum

Theory (9 min)
Rule
One dispute, one clear sum. Debt, interest and the fixed sum, each with its basis.
How it is built
  • Interest = Shortfall × 11.75 % × Days ÷ 365
  • Sum claimed = Shortfall + Interest + Fixed sum
Usual mistake
The fixed sum left out. The Act adds it to each late debt.
At work
Subcontractors use adjudication for unpaid notified sums; the notice states the dispute and the sum sought.