Theory before task 4 · 9 min

Pricing a subcontract variation

SI-07: price and submit a subcontract variation

After this lecture you can

  1. Choose the valuation basis: a subcontract rate for similar work, cost plus for new work.
  2. Build a rate from labour, materials and a percentage for overheads and profit.
  3. Price and submit a variation so it is on record with its basis.
1 / 3

Three ways to value a change

Most subcontracts follow the same ladder. Work of a similar character, in similar conditions, takes the subcontract rate. Similar work in different conditions takes an adjusted rate. Work with no similar rate is priced from cost, plus a stated percentage for overheads and profit. Daywork is the last resort, for work that cannot be measured.

2 / 3

Building a rate from cost

Take the labour hours per unit at the labour rate, add the materials per unit, then add the percentage. Round the rate, then multiply by the quantity.

Example. This is a cavity closer at a door opening, not the fire-stopping in your task.
Labour, 0.40 h at 32.00£12.80
Materials per metre£4.10
Overheads and profit£2.03
Rate per metre£18.93
Common mistake

Overheads twice

A subcontract rate already includes overheads and profit. Adding the percentage to work priced at that rate charges them twice, and the main contractor's QS will strike the whole variation back to a figure of their own. Add the percentage only to what you built up from cost.

Example. Write the basis on each line: 'MS-02 rate' or 'cost + 12 %'.

A small change, two bases

Different numbers from your task: a block infill to a redundant door opening.

Not to scale
The problem
  • Infill 2.4 m2 of 140 mm dense block, like MS-02 at £52.80/m2.
  • Cavity closer 1.8 m, a new item built up at £18.93/m including 12 %.
Step 1 of 3

Infill

Price of the infill?

2.4 × £52.80 = £126.72. No percentage: the rate already has it.

Step 2 of 3

Closer

Price of the closer?

1.8 × £18.93 = £34.07.

Step 3 of 3

Total

Total of the variation?

£126.72 + £34.07 = £160.79.

In short. Similar work at the rate; new work from cost plus the percentage; one total, each line with its basis.

Check yourself

Question 1 of 3

A new 140 mm dense block wall in a plant room. Which rate?

  • A different wall.

  • Right: similar character.

  • It can be measured.

Question 2 of 3

Where does the 12 % go?

  • That charges overheads twice.

  • Right.

  • New work needs its overheads and profit.

Question 3 of 3

New work costs 9.50 per metre. With 12 %, what is it worth for 6.00 m?

9.50 × 1.12 = 10.64; × 6.00 = 63.84.

Read the source