Theory before task 5 · 9 min

Adjudication, statutory interest and the fixed sum

Notice of adjudication for the unpaid sum

After this lecture you can

  1. Name the steps and time limits of statutory adjudication.
  2. Calculate simple interest under the Late Payment Act from the day after the final date.
  3. Add the right fixed sum and state one clear sum in the notice.
1 / 3

Four steps, fixed times

Either party may give notice of adjudication at any time. The adjudicator is appointed and the dispute referred within 7 days of the notice. The decision follows within 28 days of the referral; the referring party may agree to 14 more days. The decision binds until the dispute is finally settled, and courts enforce it.

Notice of adjudicationday 0
Referral, latestday 7
Decision, latest28 days after the referral
2 / 3

Interest and the fixed sum

If the subcontract sets no remedy for late payment, the Late Payment Act implies simple interest at 8 per cent over the reference rate, the Bank of England base rate on the last day of the half-year before. It runs daily from the day after the final date. On top, each late debt earns a fixed sum: 40 below 1,000, 70 from 1,000 to under 10,000, 100 above that.

Example. The base rate in this course is a case figure. Check the actual reference rate before you serve a real notice.
Common mistake

A notice that asks for everything

A notice that bundles every grievance, or a sum that does not match the paperwork, gives the other side a ground to challenge the adjudicator's jurisdiction. Refer one dispute, state the sum and its basis, and keep the arithmetic easy to check.

Example. Debt, interest with its days and rate, fixed sum: three lines and one total.

A smaller debt, the same method

Different numbers from your task.

Not to scale
The problem
  • Unpaid notified sum £2,400.00. Final date 10 May; notice on 9 June.
  • Rate 11.75% a year, simple, 365-day year.
Step 1 of 3

Days

Days from 11 May to 9 June, both counted?

21 + 9 = 30.

Step 2 of 3

Interest

Interest to 9 June?

£2,400.00 × 11.75% × 30 ÷ 365 = £23.18.

Step 3 of 3

Sum claimed

Sum in the notice?

£2,400.00 + £23.18 + £70.00 = £2,493.18.

In short. Debt, interest by the day, the fixed sum for the debt's size.

Check yourself

Question 1 of 3

Notice served on Monday. When must the referral be made?

  • Right: s108(2)(b).

  • That is the decision, from the referral.

  • The Act fixes 7 days.

Question 2 of 3

A debt of 650.00 is paid late. Which fixed sum?

  • Right: under 1,000.

  • That is from 1,000.

  • That is from 10,000.

Question 3 of 3

A debt of 3,650.00 at 10 % a year, simple, for 40 days. How much interest?

3,650.00 × 10 % × 40 ÷ 365 = 40.00.